Energy Projects Near You

Highfield Farm (17 MW solar farm)

Highfield Farm is a 17 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 June 2014; the record was last updated on 28 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWsolar farm
refusedstatus in REPD
28 July 2014record last updated
South Kestevencouncil area

Planning timeline

DateStage
12 March 2014Application submitted
19 June 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
17 MW
Status (REPD)
refused
Record last updated
28 July 2014
Operator or applicant
Private Developer
Planning authority
South Kesteven
Planning application reference
S14/0731
Site area
39.2 ha
Address (REPD)
Highfield Farm, Willoughby Road, West Willoughby, Grantham,
Council area (by location)
South Kesteven
Time to decision
14 weeks
REPD reference
1928

Earlier applications for this site

ApplicationMWSubmittedOutcome
Highfield Farm S13/21321728 August 2013withdrawn 12 March 2014

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Heath Lanesolar farm5refused2.7
Temple Hill Wind Farmwind farm15refused5.0
Ermine Street Farm solar parksolar farm32.5operational5.6
Glebe Farm Solar Farmsolar farm38.8refused6.5
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational6.8
Fulbeck Airfield Wind Farmwind farm25refused7.2
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built7.5
Solar Farm at Welby Solar Farmsolar farm46approved, not built7.8
Manor Farmbattery storage26permission expired7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9965, -0.5991).