Ash Tree Solar Farm & Battery Storage (49.9 MW)

Ash Tree Solar Farm & Battery Storage is a 49.9 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 July 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
South Kestevencouncil area

Planning timeline

DateStage
29 November 2023Application submitted
25 October 2024Refused by the planning authority
18 July 2025Planning permission granted
18 July 2025Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Low Carbon Limited
Planning authority
South Kesteven
Planning application reference
S23/2199
Site area
144.1 ha
Address (REPD)
High Dike Road Londonthorpe
Council area (by location)
South Kesteven
Time to decision
85 weeks
Contracts for Difference
AR7a
REPD reference
15396

The scheme also includes 25 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farmbattery storage26permission expired1.7
Side Barn, Church Lane Solar Farmsolar farm24approved, not built3.1
Solar Farm at Welby Solar Farmsolar farm46approved, not built3.3
High Dyke (Mill Farm)solar farm5operational3.4
Glebe Farm Solar Farmsolar farm38.8refused4.5
Heath Lanesolar farm5refused7.1
Canners Lane Energy Park, High Dikebattery storage1,000application submitted7.4
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built7.7
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9118, -0.5823).