Energy Projects Near You

Limes Farm Solar Farm & Battery Energy Storage (20 MW)

Limes Farm Solar Farm & Battery Energy Storage is a 20 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 May 2025, not yet built; the record was last updated on 20 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
20 May 2025record last updated
South Kestevencouncil area

Planning timeline

DateStage
7 February 2025Application submitted
12 May 2025Planning permission granted
12 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
20 May 2025
Operator or applicant
Downing Limited Liability Partnership
Planning authority
South Kesteven
Planning application reference
S24/2191
Site area
34.6 ha
Address (REPD)
Limes Solar Farm On Lands Circa 0.5km North Of Limes Farm Bourne
Council area (by location)
South Kesteven
Time to decision
13 weeks
REPD reference
11796

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Northorpe Fen Farm, Fen Road Solar Farmsolar farm15approved, not built5.4
Deeping St Nicholas Wind Farmwind farm16.4operational6.2
Deeping Gate Tree Nurseries solar parksolar farm13refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7717, -0.2904).