Energy Projects Near You

Deeping Gate Tree Nurseries solar park (13 MW)

Deeping Gate Tree Nurseries solar park is a 13 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 December 2013; the record was last updated on 24 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13 MWsolar farm
refusedstatus in REPD
24 January 2014record last updated
South Kestevencouncil area

Planning timeline

DateStage
23 August 2013Application submitted
11 December 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
13 MW
Status (REPD)
refused
Record last updated
24 January 2014
Operator or applicant
Lark Energy
Planning authority
South Kesteven
Planning application reference
S13/2242
Site area
29.2 ha
Address (REPD)
Land adj. Deeping Gate Tree Nurseries, Northfield Road, Market Deeping
Council area (by location)
South Kesteven
Time to decision
16 weeks
REPD reference
1434

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Northorpe Fen Farm, Fen Road Solar Farmsolar farm15approved, not built6.9
Deeping St Nicholas Wind Farmwind farm16.4operational7.1
Limes Farm Solar Farm & Battery Energy Storagesolar farm20approved, not built8.8
Mallard Pass Solar Farmsolar farm350approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6933, -0.3096).