Solar, wind and battery projects near Peterborough (PE6)

28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE6 (Peterborough): 17 approved but not yet running, 3 operational. The largest live scheme is Dogsthorpe, Welland Road Solar Farm & Battery Storage (14 MW solar farm, approved on 21 June 2024, not yet built), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28projects within 10 km
0awaiting a decision
17approved, not running
3operational

Projects within 10 km of PE6

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Baker Perkins, Manor Driverooftop solarrooftop solar1.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Peterborough5.1
Deeping Gate Tree Nurseries solar parksolar farmsolar farm13refusedupdated Jan 2014Aug 2013refused Dec 2013Jan 2014South Kesteven5.6
Farms of Newboroughsolar farmsolar farm49application withdrawnupdated Jul 2015Dec 2012—Jul 2015Peterborough5.7
Hundred Road Wind Turbineswind farmwind farm6appeal withdrawnupdated Sep 2015Jun 2011refused Nov 2014Sep 2015Peterborough5.8
Coningsby Business Park, Stirling Wayrooftop solarrooftop solar1.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Peterborough6.0
Dogsthorpe, Welland Road Solar Farm & Battery Storagesolar farmsolar farm14approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024Peterborough6.9
Deeping St Nicholas Wind Farmwind farmwind farm16.4operationalupdated Dec 2017Feb 2002granted May 2003Dec 2017South Holland8.4
Perkins Engines, Fengate Solar Farmsolar farmsolar farm1.2approved, not built may be out of dateupdated Mar 2022Dec 2021granted Mar 2022Mar 2022Peterborough8.6
Decoy Farmsolar farmsolar farm5operationalupdated Jul 2016May 2014granted Aug 2014Jul 2016South Holland9.1
America Farmsolar farmsolar farm8application withdrawnupdated Jul 2014Dec 2012—Jul 2014Peterborough9.4
Willow Hall Farmwind farmwind farm10application withdrawnupdated Dec 2015Jun 2014—Dec 2015Peterborough9.5
French Farmwind farmwind farm4operationalupdated Dec 2016Nov 2008granted Sep 2010Dec 2016Peterborough9.9
Gores Wind Farmwind farmwind farm16application withdrawnupdated Nov 2015Apr 2013—Nov 2015Peterborough9.9
French Farm 2 (Extension)wind farmwind farm8refusedupdated Sep 2015Jun 2013granted Feb 2014Sep 2015Peterborough10.0
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crease Drove, Crowland - Micro Energy storagebattery storagebattery storage0.2approved, not builtupdated Jan 2025Oct 2024granted Jan 2025Jan 2025South Holland5.1
Lincoln Roadbattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Peterborough5.5
Dukesmead Road, Dukesmead Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Peterborough5.7
Coningsby Business Park, Stirling Wayrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Peterborough6.0
Stirling Way, Brettonrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Peterborough6.0
Joice And Hill Poultry Solar PV Farmrooftop solarrooftop solar0.5approved, not builtupdated Oct 2022Feb 2022granted Apr 2022Oct 2022Peterborough6.1
Postland Road, James Roadbattery storagebattery storage0.2approved, not builtupdated May 2026Oct 2025granted Mar 2026May 2026South Holland6.6
F P Smith Motors, Sturrock Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Peterborough6.8
Dogsthorpe, Welland Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024Peterborough6.9
Peterborough Regional College, Park Crescentrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Peterborough8.0
Rightwell West, Bretton - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Peterborough8.1
Vicarage Farmbattery storagebattery storage0.2application withdrawnupdated Aug 2025Jul 2025—Aug 2025Peterborough9.2
Vicarage Farmbattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Peterborough9.3
Inclusive, Titan Drive - Micro Energy storage facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Peterborough9.9

Distance from the average position of the PE6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6021115.2
Rooftop solar707004.3
Wind farm600210
Battery storage908001.4

MW in pipeline: pending, approved and under-construction capacity.

How Peterborough decides solar, wind and battery applications

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Peterborough

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE6, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.