Solar, wind and battery projects near Peterborough (PE5)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE5 (Peterborough): 24 approved but not yet running. The largest live scheme is Third Drove, Fengate (50 MW battery storage, approved on 5 January 2023, not yet built; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PE5
Projects of 1 MW and more (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Coningsby Business Park, Stirling Wayrooftop solar | rooftop solar | 1.3 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Peterborough | 5.8 |
| J S Davidson Limited, Shrewsbury Avenuerooftop solar | rooftop solar | 1.4 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 | Peterborough | 6.5 |
| Wittering Ford Roadbattery storage | battery storage | 3 | approved, not built may be out of dateupdated Dec 2019 | Sep 2019 | granted Nov 2019 | Dec 2019 | Peterborough | 6.5 |
| Wittering Ford Road, Barnack Solar Photovoltaic Farmsolar farm | solar farm | 11 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Nov 2023 | Nov 2023 | Peterborough | 6.8 |
| Land at Wittering Ford Roadsolar farm | solar farm | 3.9 | permission expiredupdated Apr 2020 | Jan 2015 | granted Jan 2016 | Apr 2020 | Peterborough | 7.1 |
| Dogsthorpe, Welland Road Solar Farm & Battery Storagesolar farm | solar farm | 14 | approved, not builtupdated Jul 2024 | Nov 2023 | granted Jun 2024 | Jul 2024 | Peterborough | 7.8 |
| Baker Perkins, Manor Driverooftop solar | rooftop solar | 1.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Peterborough | 8.4 |
| Kingston Parkrooftop solar | rooftop solar | 1.8 | permission expiredupdated Feb 2020 | Jul 2018 | — | Feb 2020 | Peterborough | 8.4 |
| Perkins Engines, Fengate Solar Farmsolar farm | solar farm | 1.2 | approved, not built may be out of dateupdated Mar 2022 | Dec 2021 | granted Mar 2022 | Mar 2022 | Peterborough | 9.2 |
| Third Drove, Fengatebattery storage | battery storage | 50 | approved, not built may be out of dateupdated Jan 2026 | Jun 2022 | granted Jan 2023 | Jan 2026 | Peterborough | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| David Lloyd Clubs, Thorpe Woodrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2023 | Jun 2023 | granted Aug 2023 | Dec 2023 | Peterborough | 3.6 |
| Veolia Water Technologies, Newcombe Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2025 | Oct 2025 | granted Nov 2025 | Oct 2025 | Peterborough | 4.5 |
| Rightwell West, Bretton - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Peterborough | 4.7 |
| Nene Park Academy, Orton Longueville - Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Oct 2022 | Sep 2022 | granted Oct 2022 | Oct 2022 | Peterborough | 5.1 |
| Bringhurst, Orton Goldhaybattery storage | battery storage | 0.2 | application withdrawnupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Peterborough | 5.4 |
| Coningsby Business Park, Stirling Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Peterborough | 5.8 |
| Stirling Way, Brettonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Peterborough | 5.8 |
| Strada Alwalton Hillrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2022 | May 2022 | granted Jul 2022 | Jul 2022 | Peterborough | 5.9 |
| F P Smith Motors, Sturrock Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Peterborough | 6.0 |
| Dukesmead Road, Dukesmead Industrial Estatebattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2025 | Jul 2025 | granted Sep 2025 | Oct 2025 | Peterborough | 6.1 |
| Lincoln Roadbattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | Peterborough | 6.4 |
| Kiddicare, Club Way Solar Panlesrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | Peterborough | 7.2 |
| Dogsthorpe, Welland Road Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Nov 2023 | granted Jun 2024 | Jul 2024 | Peterborough | 7.8 |
| Peterborough Regional College, Park Crescentrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Dec 2025 | Dec 2025 | Peterborough | 8.2 |
| Vicarage Farmbattery storage | battery storage | 0.2 | application withdrawnupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Peterborough | 9.3 |
| Imperial Way, Eagle Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Huntingdonshire | 9.4 |
| Vicarage Farmbattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | Peterborough | 9.4 |
| Inclusive, Titan Drive - Micro Energy storage facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 | Peterborough | 9.6 |
Distance from the average position of the PE5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 0 | 3 | 0 | 0 | 26.2 |
| Rooftop solar | 14 | 0 | 13 | 0 | 0 | 7.9 |
| Battery storage | 10 | 0 | 8 | 0 | 0 | 54 |
MW in pipeline: pending, approved and under-construction capacity.
How Peterborough decides solar, wind and battery applications
| Applications | Peterborough | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 6 (17%) | 19% |
| Solar refused | 0 of 19 | 12% |
| Onshore wind refused | 6 of 6 | 45% |
| Battery storage refused | 0 of 10 | 16% |
| Median time from submission to decision | 12.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE5, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.