Energy Projects Near You

Solar, wind and battery projects near Peterborough (PE1)

37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE1 (Peterborough): 26 approved but not yet running, 2 operational. The largest live scheme is Third Drove, Fengate (50 MW battery storage, approved on 5 January 2023, not yet built; REPD status may be out of date), 2.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37projects within 10 km
0awaiting a decision
26approved, not running
2operational

Projects within 10 km of PE1

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dogsthorpe, Welland Road Solar Farm & Battery Storagesolar farmsolar farm14approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024Peterborough1.2
Perkins Engines, Fengate Solar Farmsolar farmsolar farm1.2approved, not built may be out of dateupdated Mar 2022Dec 2021granted Mar 2022Mar 2022Peterborough1.5
Third Drove, Fengatebattery storagebattery storage50approved, not built may be out of dateupdated Jan 2026Jun 2022granted Jan 2023Jan 2026Peterborough2.8
Baker Perkins, Manor Driverooftop solarrooftop solar1.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Peterborough3.0
Coningsby Business Park, Stirling Wayrooftop solarrooftop solar1.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Peterborough3.9
America Farmsolar farmsolar farm8application withdrawnupdated Jul 2014Dec 2012—Jul 2014Peterborough4.0
J S Davidson Limited, Shrewsbury Avenuerooftop solarrooftop solar1.4approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Peterborough4.3
Kingston Parkrooftop solarrooftop solar1.8permission expiredupdated Feb 2020Jul 2018—Feb 2020Peterborough4.9
Whittleseywind farmwind farm9operationalupdated Jul 2012Apr 2007granted Jul 2007Jul 2012Fenland5.4
Kings Dyke, Whittleseybattery storagebattery storage10approved, not builtupdated May 2025Nov 2024granted May 2025May 2025Fenland5.8
Willow Hall Farmwind farmwind farm10application withdrawnupdated Dec 2015Jun 2014—Dec 2015Peterborough6.2
Haddon Solar parksolar farmsolar farm22refusedupdated Feb 2024May 2022refused Jan 2024Feb 2024Huntingdonshire7.3
Black Bush Farmsolar farmsolar farm2.7operationalupdated Nov 2014Mar 2011granted Mar 2012Nov 2014Fenland7.3
Gores Wind Farmwind farmwind farm16application withdrawnupdated Nov 2015Apr 2013—Nov 2015Peterborough7.3
Farms of Newboroughsolar farmsolar farm49application withdrawnupdated Jul 2015Dec 2012—Jul 2015Peterborough7.7
Hundred Road Wind Turbineswind farmwind farm6appeal withdrawnupdated Sep 2015Jun 2011refused Nov 2014Sep 2015Peterborough9.2
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Peterborough Regional College, Park Crescentrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Peterborough0.5
Dogsthorpe, Welland Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024Peterborough1.2
Vicarage Farmbattery storagebattery storage0.2application withdrawnupdated Aug 2025Jul 2025—Aug 2025Peterborough1.8
Vicarage Farmbattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Peterborough1.9
Inclusive, Titan Drive - Micro Energy storage facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Peterborough2.4
F P Smith Motors, Sturrock Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Peterborough2.7
Rightwell West, Bretton - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Peterborough3.3
Lincoln Roadbattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Peterborough3.9
Coningsby Business Park, Stirling Wayrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Peterborough3.9
Stirling Way, Brettonrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Peterborough3.9
Dukesmead Road, Dukesmead Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Peterborough4.1
Joice And Hill Poultry Solar PV Farmrooftop solarrooftop solar0.5approved, not builtupdated Oct 2022Feb 2022granted Apr 2022Oct 2022Peterborough4.2
David Lloyd Clubs, Thorpe Woodrooftop solarrooftop solar—approved, not builtupdated Dec 2023Jun 2023granted Aug 2023Dec 2023Peterborough4.6
Kiddicare, Club Way Solar Panlesrooftop solarrooftop solar1approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Peterborough4.6
Nene Park Academy, Orton Longueville - Photovoltaic Panelsrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Oct 2022Sep 2022granted Oct 2022Oct 2022Peterborough4.9
Bringhurst, Orton Goldhaybattery storagebattery storage0.2application withdrawnupdated Sep 2025Jul 2025—Sep 2025Peterborough5.3
Johnsons Aggregates And Recycling, Peterborough Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Fenland6.4
Imperial Way, Eagle Business Parkrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Huntingdonshire6.8
Veolia Water Technologies, Newcombe Wayrooftop solarrooftop solar0.3approved, not builtupdated Oct 2025Oct 2025granted Nov 2025Oct 2025Peterborough6.9
Strada Alwalton Hillrooftop solarrooftop solar0.7approved, not builtupdated Jul 2022May 2022granted Jul 2022Jul 2022Peterborough7.5
Crease Drove, Crowland - Micro Energy storagebattery storagebattery storage0.2approved, not builtupdated Jan 2025Oct 2024granted Jan 2025Jan 2025South Holland9.9

Distance from the average position of the PE1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6021115.2
Rooftop solar16015008.6
Wind farm400100
Battery storage11090061.2

MW in pipeline: pending, approved and under-construction capacity.

How Peterborough decides solar, wind and battery applications

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Peterborough

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE1, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.