Energy Projects Near You

Haddon Solar park (22 MW)

Haddon Solar park is a 22 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 January 2024; the record was last updated on 5 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
refusedstatus in REPD
5 February 2024record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
13 May 2022Application submitted
23 January 2024Refused by the planning authority

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
refused
Record last updated
5 February 2024
Operator or applicant
Wessex Solar Energy
Planning authority
Huntingdonshire
Planning application reference
22/00668/FUL
Site area
46.0 ha
Address (REPD)
Land North East Of Bates Lodge Peterborough Road Haddon
Council area (by location)
Huntingdonshire
Time to decision
89 weeks
REPD reference
8477

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kings Dyke, Whittleseybattery storage10approved, not built3.1
Whittleseywind farm9operational3.2
Third Drove, Fengatebattery storage50approved, not built4.7
Glass moor Extensionwind farm12operational5.1
Glass Moorwind farm16operational5.1
America Farmsolar farm8application withdrawn6.3
Ramsey Wind Farm Extensionwind farm8operational8.0
Willow Hall Farmwind farm10application withdrawn8.0
Dogsthorpe, Welland Road Solar Farm & Battery Storagesolar farm14approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5302, -0.1817).