Glass moor Extension (12 MW wind farm)

Glass moor Extension is a 12 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 18 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
18 December 2014record last updated
Fenlandcouncil area

Planning timeline

DateStage
31 January 2011Application submitted
10 April 2012Planning permission granted
1 September 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
18 December 2014
Operator or applicant
EDF/China General Nuclear Power Corporation
Planning authority
Fenland
Planning application reference
F/YR11/0094/F
Turbines
6
Address (REPD)
S/E Of Yewtree Farm, Glassmoor Bank, Whittlesey, Cambridge, Cambridgeshire
Council area (by location)
Fenland
Time to decision
62 weeks
REPD reference
3765

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glass Moorwind farm16operational<0.1
Haddon Solar parksolar farm22refused5.1
Burnt House Farmwind farm6operational5.5
Ramsey Wind Farm Extensionwind farm8operational5.7
Turves Solar Farmsolar farm5operational5.7
Kings Dyke, Whittleseybattery storage10approved, not built5.8
Whittleseywind farm9operational6.1
Floods Ferry Farmwind farm18refused on appeal7.2
Bury Green Farm Solarsolar farm5operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5186, -0.1088).