Whittlesey (9 MW wind farm)

Whittlesey is a 9 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 September 2008; the record was last updated on 4 July 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
operationalstatus in REPD
4 July 2012record last updated
Fenlandcouncil area

Planning timeline

DateStage
13 April 2007Application submitted
9 July 2007Planning permission granted
1 November 2007Construction started
3 September 2008Operational

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
4 July 2012
Operator or applicant
REG Windpower (previously Cornwall Light and Power)
Planning authority
Fenland
Planning application reference
F/YR07/0413/F
Turbines
3
Address (REPD)
McCain's Food, Funtham's Lane, Whittlesey, Peterborough
Council area (by location)
Fenland
Time to decision
12 weeks
REPD reference
3021

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kings Dyke, Whittleseybattery storage10approved, not built0.4
Third Drove, Fengatebattery storage50approved, not built2.6
Haddon Solar parksolar farm22refused3.2
America Farmsolar farm8application withdrawn3.2
Willow Hall Farmwind farm10application withdrawn4.9
Gores Wind Farmwind farm16application withdrawn5.8
Glass Moorwind farm16operational6.1
Glass moor Extensionwind farm12operational6.1
Dogsthorpe, Welland Road Solar Farm & Battery Storagesolar farm14approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.558, -0.1719).