Gores Wind Farm (16 MW)
Gores Wind Farm is a 16 MW wind farm project in Peterborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 28 October 2015; the record was last updated on 5 November 2015.
16 MWwind farm
application withdrawnstatus in REPD
5 November 2015record last updated
Peterboroughcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 April 2013 | Application submitted |
| 28 October 2015 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 16 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 5 November 2015
- Operator or applicant
- Peterborough Wind Energy
- Planning authority
- Peterborough
- Planning application reference
- 13/00431/FUL
- Turbines
- 8
- Address (REPD)
- Gores Farm Whittlesey Road Thorney Peterborough
- Council area (by location)
- Peterborough
- REPD reference
- 3921
Who decides
| Applications | Peterborough | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 6 (17%) | 19% |
| Solar refused | 0 of 19 | 12% |
| Onshore wind refused | 6 of 6 | 45% |
| Battery storage refused | 0 of 10 | 16% |
| Median time from submission to decision | 12.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Willow Hall Farm | wind farm | 10 | application withdrawn | 1.1 |
| America Farm | solar farm | 8 | application withdrawn | 3.5 |
| Morris Fen (Wind) | wind farm | 16 | refused | 4.4 |
| Morris Fen (PV) | solar farm | 27 | application withdrawn | 4.6 |
| Farms of Newborough | solar farm | 49 | application withdrawn | 4.9 |
| Whittlesey | wind farm | 9 | operational | 5.8 |
| Kings Dyke, Whittlesey | battery storage | 10 | approved, not built | 5.8 |
| Hundred Road Wind Turbines | wind farm | 6 | appeal withdrawn | 6.1 |
| Third Drove, Fengate | battery storage | 50 | approved, not built | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6042, -0.1335).