Energy Projects Near You

Gores Wind Farm (16 MW)

Gores Wind Farm is a 16 MW wind farm project in Peterborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 28 October 2015; the record was last updated on 5 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
application withdrawnstatus in REPD
5 November 2015record last updated
Peterboroughcouncil area

Planning timeline

DateStage
5 April 2013Application submitted
28 October 2015Application withdrawn

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
application withdrawn
Record last updated
5 November 2015
Operator or applicant
Peterborough Wind Energy
Planning authority
Peterborough
Planning application reference
13/00431/FUL
Turbines
8
Address (REPD)
Gores Farm Whittlesey Road Thorney Peterborough
Council area (by location)
Peterborough
REPD reference
3921

Who decides

ApplicationsPeterboroughUK
Decided applications (solar, wind, battery)3510,236
Refused6 (17%)19%
Solar refused0 of 1912%
Onshore wind refused6 of 645%
Battery storage refused0 of 1016%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Willow Hall Farmwind farm10application withdrawn1.1
America Farmsolar farm8application withdrawn3.5
Morris Fen (Wind)wind farm16refused4.4
Morris Fen (PV)solar farm27application withdrawn4.6
Farms of Newboroughsolar farm49application withdrawn4.9
Whittleseywind farm9operational5.8
Kings Dyke, Whittleseybattery storage10approved, not built5.8
Hundred Road Wind Turbineswind farm6appeal withdrawn6.1
Third Drove, Fengatebattery storage50approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6042, -0.1335).