Energy Projects Near You

Glass Moor (16 MW wind farm)

Glass Moor is a 16 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2005; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Fenlandcouncil area

Planning timeline

DateStage
25 November 2002Application submitted
30 May 2003Planning permission granted
1 December 2005Operational

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Fenland Windfarms Ltd
Planning authority
Fenland
Planning application reference
S/YR02/1327
Turbines
8
Address (REPD)
Glass Moor Near Pondersbridge Cambridgeshire
Council area (by location)
Fenland
Time to decision
27 weeks
REPD reference
3132

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glass moor Extensionwind farm12operational<0.1
Haddon Solar parksolar farm22refused5.1
Burnt House Farmwind farm6operational5.5
Ramsey Wind Farm Extensionwind farm8operational5.7
Turves Solar Farmsolar farm5operational5.7
Kings Dyke, Whittleseybattery storage10approved, not built5.8
Whittleseywind farm9operational6.1
Floods Ferry Farmwind farm18refused on appeal7.2
Bury Green Farm Solarsolar farm5operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5186, -0.1088).