Glass Moor (16 MW wind farm)
Glass Moor is a 16 MW wind farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2005; the record was last updated on 6 May 2009.
16 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Fenlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 25 November 2002 | Application submitted |
| 30 May 2003 | Planning permission granted |
| 1 December 2005 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 16 MW
- Status (REPD)
- operational
- Record last updated
- 6 May 2009
- Operator or applicant
- Fenland Windfarms Ltd
- Planning authority
- Fenland
- Planning application reference
- S/YR02/1327
- Turbines
- 8
- Address (REPD)
- Glass Moor Near Pondersbridge Cambridgeshire
- Council area (by location)
- Fenland
- Time to decision
- 27 weeks
- REPD reference
- 3132
Who decides
| Applications | Fenland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 10 (20%) | 19% |
| Solar refused | 3 of 23 | 12% |
| Onshore wind refused | 6 of 21 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 23.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Glass moor Extension | wind farm | 12 | operational | <0.1 |
| Haddon Solar park | solar farm | 22 | refused | 5.1 |
| Burnt House Farm | wind farm | 6 | operational | 5.5 |
| Ramsey Wind Farm Extension | wind farm | 8 | operational | 5.7 |
| Turves Solar Farm | solar farm | 5 | operational | 5.7 |
| Kings Dyke, Whittlesey | battery storage | 10 | approved, not built | 5.8 |
| Whittlesey | wind farm | 9 | operational | 6.1 |
| Floods Ferry Farm | wind farm | 18 | refused on appeal | 7.2 |
| Bury Green Farm Solar | solar farm | 5 | operational | 7.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5186, -0.1088).