Bury Green Farm Solar (5 MW)

Bury Green Farm Solar is a 5 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 29 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
29 July 2016record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
18 May 2015Application submitted
25 September 2015Planning permission granted
18 January 2016Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
29 July 2016
Operator or applicant
Bury Green Farm Solar (Caledon Partners)
Planning authority
Huntingdonshire
Planning application reference
15/00790/FUL
Site area
10.0 ha
Address (REPD)
New Fen Road Lane, Ramsey
Council area (by location)
Huntingdonshire
Time to decision
19 weeks
REPD reference
6180

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Biggin Lanesolar farm5operational0.8
Little Staughton Solar Farmsolar farm50approved, not built2.0
Ramsey Wind Farm Extensionwind farm8operational2.1
Red House Farm Solar Farmsolar farm20approved, not built7.3
Abbey Farmsolar farm9operational7.6
Red Tilewind farm24operational7.7
Glass moor Extensionwind farm12operational7.7
Glass Moorwind farm16operational7.7
Abbots Ripton Solar Farmsolar farm24.7operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4514, -0.137).