Red Tile (24 MW wind farm)

Red Tile is a 24 MW wind farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2006; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
operationalstatus in REPD
4 December 2017record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
15 October 2003Application submitted
7 February 2005Planning permission granted
1 May 2006Construction started
1 December 2006Operational

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Wind Prospect Developments
Planning authority
Huntingdonshire
Planning application reference
0302827FUL
Turbines
12
Address (REPD)
Land Adjacent to Broadpool Farm High Fen Straight Drove Warboys Huntingdon
Council area (by location)
Huntingdonshire
Time to decision
69 weeks
REPD reference
3608

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Staughton Solar Farmsolar farm50approved, not built5.7
Land at Biggin Lanesolar farm5operational7.2
Ramsey Wind Farm Extensionwind farm8operational7.6
Bury Green Farm Solarsolar farm5operational7.7
Wiggin Hill Solar Farm - Phase 1solar farm6.8operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4305, -0.0292).