Energy Projects Near You

Wiggin Hill Solar Farm - Phase 1 (6.8 MW)

Wiggin Hill Solar Farm - Phase 1 is a 6.8 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
20 November 2012Application submitted
19 February 2013Planning permission granted
14 November 2014Construction started
14 March 2015Operational

Project details

Technology
solar farm
Capacity
6.8 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Huntingdonshire
Planning application reference
1201911FUL
Site area
11.3 ha
Address (REPD)
Land North Of Wiggin Hill Old Ramsey Road St Ives
Council area (by location)
Huntingdonshire
Time to decision
13 weeks
REPD reference
1865

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abbots Ripton Solar Farmsolar farm24.7operational8.6
Red Tilewind farm24operational8.9
Cambridge Wind Farmwind farm32refused on appeal9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3557, -0.0774).