Cambridge Wind Farm (32 MW)
Cambridge Wind Farm is a 32 MW wind farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 December 2006; the record was last updated on 2 November 2011.
32 MWwind farm
refused on appealstatus in REPD
2 November 2011record last updated
South Cambridgeshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 August 2004 | Application submitted |
| 7 April 2005 | Refused by the planning authority |
| 8 December 2006 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 32 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 2 November 2011
- Operator or applicant
- Your Energy
- Planning authority
- South Cambridgeshire
- Planning application reference
- S/1663/04/F
- Appeal reference
- S/1663/04/F
- Turbines
- 16
- Address (REPD)
- L and South West of Huntingdon, Bosworth and Conningham
- Council area (by location)
- South Cambridgeshire
- Time to decision
- 34 weeks
- REPD reference
- 3230
Who decides
| Applications | South Cambridgeshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 48 | 10,236 |
| Refused | 10 (21%) | 19% |
| Solar refused | 6 of 40 | 12% |
| Onshore wind refused | 4 of 5 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Stargoose Farm Solar Farm | solar farm | 50 | approved, not built | 4.2 |
| Stargoose Farm | battery storage | 312 | approved, not built | 4.2 |
| Cambridge Solar Farm | solar farm | 49.9 | refused | 4.4 |
| Falcon Park, Wilsons Road Solar Farm & Battery Energy Storage | solar farm | 26 | application submitted | 5.5 |
| Bourn Solar Farm | solar farm | 5 | refused | 7.5 |
| Skylark Meadow Solar park | solar farm | 5 | operational | 8.8 |
| Wiggin Hill Solar Farm - Phase 1 | solar farm | 6.8 | operational | 9.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2762, -0.0326).