Solar, wind and battery projects near St Ives (PE27)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE27 (Huntingdonshire): 9 approved but not yet running, 4 operational. The largest live scheme is Meadow Lane Park and Ride (0.9 MW solar farm, under construction since 25 March 2022), 1.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PE27
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wiggin Hill Solar Farm - Phase 1solar farm | solar farm | 6.8 | operationalupdated May 2015 | Nov 2012 | granted Feb 2013 | May 2015 | Huntingdonshire | 2.7 |
| Wiggin Hill Solar Farm - Phase 2solar farm | solar farm | 4.1 | operationalupdated May 2015 | Nov 2013 | granted Feb 2014 | May 2015 | Huntingdonshire | 2.7 |
| Lodge Farmsolar farm | solar farm | 2.4 | operationalupdated Mar 2016 | Jun 2014 | granted Sep 2014 | Mar 2016 | Huntingdonshire | 5.9 |
| Cambridge Wind Farmwind farm | wind farm | 32 | refused on appealupdated Nov 2011 | Aug 2004 | refused Apr 2005 | Nov 2011 | South Cambridgeshire | 6.7 |
| Abbots Ripton Solar Farm (ext.)solar farm | solar farm | 3.9 | operationalupdated Sep 2016 | Dec 2014 | granted Jul 2015 | Sep 2016 | Huntingdonshire | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| One Leisure Indoor, Westwood Road Solar Car Park Canopiessolar farm | solar farm | — | approved, not builtupdated Jan 2025 | Dec 2024 | granted Jan 2025 | Jan 2025 | Huntingdonshire | 1.0 |
| Meadow Lane Park and Ridesolar farm | solar farm | 0.9 | under constructionupdated Mar 2022 | Apr 2017 | — | Mar 2022 | Huntingdonshire | 1.1 |
| Meadow Lane Park and Ridebattery storage | battery storage | — | under constructionupdated Sep 2022 | Apr 2017 | — | Sep 2022 | Huntingdonshire | 1.1 |
| Needingworth Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2022 | Nov 2021 | granted Jan 2022 | Feb 2022 | Huntingdonshire | 1.3 |
| J Sainsbury Plc, St Germain Walkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Huntingdonshire | 7.5 |
| Bridge Farm, Earith Fen Droverooftop solar | rooftop solar | 0.2 | application withdrawnupdated Nov 2025 | Jul 2025 | — | Nov 2025 | Huntingdonshire | 7.6 |
| Bridge Farm, Drove Colnerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Huntingdonshire | 7.6 |
| Latham Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | Huntingdonshire | 8.2 |
| Hilton Food Group, Latham Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Huntingdonshire | 8.2 |
| Lancaster House, Lancaster Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Oct 2023 | granted Jan 2024 | Feb 2024 | Huntingdonshire | 8.9 |
Distance from the average position of the PE27 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 0 | 2 | 4 | 0 | 0.9 |
| Rooftop solar | 7 | 0 | 6 | 0 | 0 | 2.8 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Huntingdonshire decides solar, wind and battery applications
| Applications | Huntingdonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 7 (15%) | 19% |
| Solar refused | 1 of 33 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
All projects in Huntingdonshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.