Energy Projects Near You

Solar, wind and battery projects near Huntingdon (PE28)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE28 (Huntingdonshire): 10 approved but not yet running, 7 operational. The largest live scheme is Red House Farm Solar Farm (20 MW solar farm, approved on 7 December 2021, not yet built; REPD status may be out of date), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
0awaiting a decision
10approved, not running
7operational

Projects within 10 km of PE28

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Abbots Ripton Solar Farm (ext.)solar farmsolar farm3.9operationalupdated Sep 2016Dec 2014granted Jul 2015Sep 2016Huntingdonshire1.5
Abbots Ripton Solar Farmsolar farmsolar farm24.7operationalupdated Mar 2015Aug 2013granted Oct 2013Mar 2015Huntingdonshire2.2
Lodge Farmsolar farmsolar farm2.4operationalupdated Mar 2016Jun 2014granted Sep 2014Mar 2016Huntingdonshire4.2
Red House Farm Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Dec 2021Aug 2021granted Dec 2021Dec 2021Huntingdonshire7.0
Abbey Farmsolar farmsolar farm9operationalupdated Apr 2014Jan 2013granted Sep 2013Apr 2014Huntingdonshire7.4
Wiggin Hill Solar Farm - Phase 2solar farmsolar farm4.1operationalupdated May 2015Nov 2013granted Feb 2014May 2015Huntingdonshire7.6
Wiggin Hill Solar Farm - Phase 1solar farmsolar farm6.8operationalupdated May 2015Nov 2012granted Feb 2013May 2015Huntingdonshire7.7
Woolley Hill Wind Farmwind farmwind farm10operationalupdated Nov 2016Nov 2010granted Mar 2012Nov 2016Huntingdonshire8.2
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hilton Food Group, Latham Roadrooftop solarrooftop solar0.8approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Huntingdonshire1.3
Latham Roadrooftop solarrooftop solar0.9approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Huntingdonshire1.3
Lancaster House, Lancaster Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Oct 2023granted Jan 2024Feb 2024Huntingdonshire1.5
J Sainsbury Plc, St Germain Walkrooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Huntingdonshire3.2
Alconbury Packing Solutionsrooftop solarrooftop solar1approved, not builtupdated Apr 2022Apr 2022granted Jul 2022Apr 2022Huntingdonshire4.1
Founders House, Pierson Roadrooftop solarrooftop solar1approved, not builtupdated Mar 2023Dec 2022granted Jan 2023Mar 2023Huntingdonshire4.1
One Leisure Indoor, Westwood Road Solar Car Park Canopiessolar farmsolar farm—approved, not builtupdated Jan 2025Dec 2024granted Jan 2025Jan 2025Huntingdonshire7.9
Meadow Lane Park and Ridesolar farmsolar farm0.9under constructionupdated Mar 2022Apr 2017—Mar 2022Huntingdonshire9.5
Meadow Lane Park and Ridebattery storagebattery storage—under constructionupdated Sep 2022Apr 2017—Sep 2022Huntingdonshire9.5

Distance from the average position of the PE28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm9036020.9
Rooftop solar606004.2
Wind farm100100
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Huntingdonshire decides solar, wind and battery applications

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Huntingdonshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE28, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.