Energy Projects Near You

Solar, wind and battery projects near Huntingdon (PE29)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE29 (Huntingdonshire): 1 is waiting for a planning decision, 10 approved but not yet running, 8 operational. The largest live scheme is Vicarage Lane, Diddington Solar Arrays (35 MW solar farm, application submitted on 2 August 2023, no decision recorded; REPD status may be out of date), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
1awaiting a decision
10approved, not running
8operational

Projects within 10 km of PE29

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Abbots Ripton Solar Farm (ext.)solar farmsolar farm3.9operationalupdated Sep 2016Dec 2014granted Jul 2015Sep 2016Huntingdonshire4.6
Lodge Farmsolar farmsolar farm2.4operationalupdated Mar 2016Jun 2014granted Sep 2014Mar 2016Huntingdonshire5.3
Abbots Ripton Solar Farmsolar farmsolar farm24.7operationalupdated Mar 2015Aug 2013granted Oct 2013Mar 2015Huntingdonshire5.3
Wiggin Hill Solar Farm - Phase 2solar farmsolar farm4.1operationalupdated May 2015Nov 2013granted Feb 2014May 2015Huntingdonshire7.3
Wiggin Hill Solar Farm - Phase 1solar farmsolar farm6.8operationalupdated May 2015Nov 2012granted Feb 2013May 2015Huntingdonshire7.4
Cotton Farmwind farmwind farm20operationalupdated Jan 2015Aug 2008granted Dec 2010Jan 2015Huntingdonshire7.9
Vicarage Lane, Diddington Solar Arrayssolar farmsolar farm35application submitted may be out of dateupdated Aug 2023Aug 2023—Aug 2023Huntingdonshire7.9
Woolley Hill Wind Farmwind farmwind farm10operationalupdated Nov 2016Nov 2010granted Mar 2012Nov 2016Huntingdonshire8.8
Common Barn Wind Farmwind farmwind farm6.2operationalupdated Dec 2019May 2012granted Jul 2013Dec 2019Huntingdonshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
J Sainsbury Plc, St Germain Walkrooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Huntingdonshire0.2
Latham Roadrooftop solarrooftop solar0.9approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Huntingdonshire1.9
Hilton Food Group, Latham Roadrooftop solarrooftop solar0.8approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Huntingdonshire1.9
Lancaster House, Lancaster Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Oct 2023granted Jan 2024Feb 2024Huntingdonshire2.1
One Leisure Indoor, Westwood Road Solar Car Park Canopiessolar farmsolar farm—approved, not builtupdated Jan 2025Dec 2024granted Jan 2025Jan 2025Huntingdonshire6.4
Alconbury Packing Solutionsrooftop solarrooftop solar1approved, not builtupdated Apr 2022Apr 2022granted Jul 2022Apr 2022Huntingdonshire6.7
Founders House, Pierson Roadrooftop solarrooftop solar1approved, not builtupdated Mar 2023Dec 2022granted Jan 2023Mar 2023Huntingdonshire6.7
Meadow Lane Park and Ridesolar farmsolar farm0.9under constructionupdated Mar 2022Apr 2017—Mar 2022Huntingdonshire7.8
Meadow Lane Park and Ridebattery storagebattery storage—under constructionupdated Sep 2022Apr 2017—Sep 2022Huntingdonshire7.8
Needingworth Roadrooftop solarrooftop solar0.4approved, not builtupdated Feb 2022Nov 2021granted Jan 2022Feb 2022Huntingdonshire8.6

Distance from the average position of the PE29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8125035.9
Rooftop solar707004.6
Wind farm300300
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Huntingdonshire decides solar, wind and battery applications

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Huntingdonshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE29, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.