Energy Projects Near You

Common Barn Wind Farm (6.2 MW)

Common Barn Wind Farm is a 6.2 MW wind farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 May 2019; the record was last updated on 11 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWwind farm
operationalstatus in REPD
11 December 2019record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
15 May 2012Application submitted
5 December 2012Refused by the planning authority
11 July 2013Planning permission granted
11 July 2013Appeal allowed
15 January 2018Construction started
9 May 2019Operational

Project details

Technology
wind farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
11 December 2019
Operator or applicant
TCI Renewables
Planning authority
Huntingdonshire
Planning application reference
1200803FUL
Appeal reference
1200061NONDET
Turbines
3
Address (REPD)
Church Farm, Southoe, Huntingdonshire
Council area (by location)
Huntingdonshire
Time to decision
60 weeks
Contracts for Difference
AR1
REPD reference
4076

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Vicarage Lane, Diddington Solar Arrayssolar farm35application submitted2.6
East Park Energysolar farm400application submitted3.6
Staughton Airfield Solar Farmsolar farm40operational6.3
Cotton Farmwind farm20operational6.5
Cobholden Solar Farmsolar farm49.9approved, not built6.9
Woolley Hill Wind Farmwind farm10operational7.1
Cobholden Battery Storagebattery storage100approved, not built7.2
Rookery Farm, Kimbolton Road Solar Farmsolar farm50approved, not built7.8
Rookery Farm, Kimbolton Roadbattery storage50approved, not built7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2773, -0.2877).