Common Barn Wind Farm (6.2 MW)
Common Barn Wind Farm is a 6.2 MW wind farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 May 2019; the record was last updated on 11 December 2019.
6.2 MWwind farm
operationalstatus in REPD
11 December 2019record last updated
Huntingdonshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 May 2012 | Application submitted |
| 5 December 2012 | Refused by the planning authority |
| 11 July 2013 | Planning permission granted |
| 11 July 2013 | Appeal allowed |
| 15 January 2018 | Construction started |
| 9 May 2019 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 6.2 MW
- Status (REPD)
- operational
- Record last updated
- 11 December 2019
- Operator or applicant
- TCI Renewables
- Planning authority
- Huntingdonshire
- Planning application reference
- 1200803FUL
- Appeal reference
- 1200061NONDET
- Turbines
- 3
- Address (REPD)
- Church Farm, Southoe, Huntingdonshire
- Council area (by location)
- Huntingdonshire
- Time to decision
- 60 weeks
- Contracts for Difference
- AR1
- REPD reference
- 4076
Who decides
| Applications | Huntingdonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 7 (15%) | 19% |
| Solar refused | 1 of 33 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Vicarage Lane, Diddington Solar Arrays | solar farm | 35 | application submitted | 2.6 |
| East Park Energy | solar farm | 400 | application submitted | 3.6 |
| Staughton Airfield Solar Farm | solar farm | 40 | operational | 6.3 |
| Cotton Farm | wind farm | 20 | operational | 6.5 |
| Cobholden Solar Farm | solar farm | 49.9 | approved, not built | 6.9 |
| Woolley Hill Wind Farm | wind farm | 10 | operational | 7.1 |
| Cobholden Battery Storage | battery storage | 100 | approved, not built | 7.2 |
| Rookery Farm, Kimbolton Road Solar Farm | solar farm | 50 | approved, not built | 7.8 |
| Rookery Farm, Kimbolton Road | battery storage | 50 | approved, not built | 7.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2773, -0.2877).