Energy Projects Near You

Cobholden Solar Farm (49.9 MW)

Cobholden Solar Farm is a 49.9 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 January 2025, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Bedfordcouncil area

Planning timeline

DateStage
21 May 2024Application submitted
30 January 2025Planning permission granted
30 January 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
AGR Renewables
Planning authority
Bedford
Planning application reference
24/00858/MAF
Site area
110.0 ha
Address (REPD)
South & N/O Bushmead Road, Staploe, Bedford
Council area (by location)
Bedford
Time to decision
36 weeks
Contracts for Difference
AR7a
REPD reference
9479

Recorded together with Cobholden Battery Storage (100 MW battery storage, approved, not built).

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Park Energysolar farm400application submitted3.4
Staughton Airfield Solar Farmsolar farm40operational4.3
Abbotsley Country Homes, Drewels Lane Solar Farmsolar farm49.9approved, not built5.4
Common Barn Wind Farmwind farm6.2operational6.9
Caldecote Manor Farmsolar farm5operational7.1
Weald Farm, Cambridge Road Solar Farm & Battery Storagesolar farm49.9approved, not built7.7
Vicarage Lane, Diddington Solar Arrayssolar farm35application submitted7.8
Waterloo solar parksolar farm14.6operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2168, -0.3114).