Energy Projects Near You

Waterloo solar park (14.6 MW)

Waterloo solar park is a 14.6 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2015; the record was last updated on 13 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.6 MWsolar farm
operationalstatus in REPD
13 May 2015record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
25 October 2013Application submitted
30 April 2014Planning permission granted
5 January 2015Construction started
19 March 2015Operational

Project details

Technology
solar farm
Capacity
14.6 MW
Status (REPD)
operational
Record last updated
13 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Central Bedfordshire
Planning application reference
CB/13/03549/FULL
Site area
34.6 ha
Address (REPD)
Land West of Fernbury Farm, Tempsford Road, Everton
Council area (by location)
Central Bedfordshire
Time to decision
27 weeks
REPD reference
1769

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lowfield Farm Solar Farmsolar farm26.5approved, not built1.6
Moggerhanger Road, Sandy Solar Farmsolar farm7application submitted4.2
Abbotsley Country Homes, Drewels Lane Solar Farmsolar farm49.9approved, not built5.1
Caldecote Manor Farmsolar farm5operational7.6
Dunton Lanebattery storage177approved, not built7.8
Cobholden Solar Farmsolar farm49.9approved, not built8.4
Dunton Lanebattery storage200approved, not built8.5
Solar Farm & Battery Storage at N/O Northill Roadsolar farm49.9application submitted8.9
Weald Farm, Cambridge Road Solar Farm & Battery Storagesolar farm49.9approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1493, -0.2563).