Energy Projects Near You

Lowfield Farm Solar Farm (26.5 MW)

Lowfield Farm Solar Farm is a 26.5 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 November 2025, not yet built; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26.5 MWsolar farm
approved, not builtstatus in REPD
2 December 2025record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
15 January 2025Application submitted
3 November 2025Planning permission granted
3 November 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
26.5 MW
Status (REPD)
approved, not built
Record last updated
2 December 2025
Operator or applicant
Renewable Connections Developments Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/24/03703/FULL
Address (REPD)
Lowfield Farm, Sandy
Council area (by location)
Central Bedfordshire
Time to decision
42 weeks
Name in REPD
Lowfield Farm - Solar Farm
REPD reference
16062

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Waterloo solar parksolar farm14.6operational1.6
Moggerhanger Road, Sandy Solar Farmsolar farm7application submitted3.0
Dunton Lanebattery storage177approved, not built6.5
Abbotsley Country Homes, Drewels Lane Solar Farmsolar farm49.9approved, not built6.7
Dunton Lanebattery storage200approved, not built7.2
Solar Farm & Battery Storage at N/O Northill Roadsolar farm49.9application submitted7.7
Langford Wind Farmwind farm20operational8.6
Caldecote Manor Farmsolar farm5operational9.2
Cobholden Solar Farmsolar farm49.9approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1357, -0.2637).