Langford Wind Farm (20 MW)
Langford Wind Farm is a 20 MW wind farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 January 2014; the record was last updated on 16 September 2014.
20 MWwind farm
operationalstatus in REPD
16 September 2014record last updated
Central Bedfordshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 11 February 2009 | Application submitted |
| 7 January 2011 | Refused by the planning authority |
| 19 January 2012 | Planning permission granted |
| 19 January 2012 | Appeal allowed |
| 17 February 2013 | Construction started |
| 30 January 2014 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 20 MW
- Status (REPD)
- operational
- Record last updated
- 16 September 2014
- Operator or applicant
- Co-operative Group
- Planning authority
- Central Bedfordshire
- Planning application reference
- 09/00118/FULL
- Appeal reference
- APP/P0240/A/11/2150950/NWF
- Turbines
- 10
- Address (REPD)
- Edworth Road, Langford, Biggleswade, Bedfordshire, SG18 9PJ
- Council area (by location)
- Central Bedfordshire
- Time to decision
- 153 weeks
- REPD reference
- 4666
Who decides
| Applications | Central Bedfordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 59 | 10,236 |
| Refused | 8 (14%) | 19% |
| Solar refused | 4 of 36 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Battery storage refused | 2 of 16 | 16% |
| Median time from submission to decision | 19.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Dunton Lane | battery storage | 200 | approved, not built | 2.0 |
| Langford Solar Farm | solar farm | 13 | operational | 2.1 |
| Dunton Lane | battery storage | 177 | approved, not built | 2.7 |
| Tophams Solar Farm | solar farm | 40 | approved, not built | 7.8 |
| Moggerhanger Road, Sandy Solar Farm | solar farm | 7 | application submitted | 8.6 |
| Lowfield Farm Solar Farm | solar farm | 26.5 | approved, not built | 8.6 |
| Letchworth Garden City - Urban Reserve Energy Storage Facility | battery storage | 5 | approved, not built | 8.7 |
| Solar Farm & Battery Storage at N/O Northill Road | solar farm | 49.9 | application submitted | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.059, -0.2453).