Solar, wind and battery projects near Baldock (SG7)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SG7 (North Hertfordshire): 4 are waiting for a planning decision, 15 approved but not yet running, 2 operational. The largest live scheme is Solar Panels at Nw/O Cottered & Sw/O The A507 Cottered (354 MW battery storage, application submitted on 20 December 2024, no decision recorded), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SG7
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Tophams Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | Apr 2022 | granted Jun 2024 | Feb 2026 | North Hertfordshire | 1.3 |
| Tophams Solar Farmbattery storage | battery storage | 8 | approved, not builtupdated Feb 2026 | Apr 2022 | granted Jun 2024 | Feb 2026 | North Hertfordshire | 1.3 |
| Letchworth Garden City - Urban Reserve Energy Storage Facilitybattery storage | battery storage | 5 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | North Hertfordshire | 3.4 |
| Westonwind farm | wind farm | 6 | application withdrawnupdated Nov 2007 | Dec 2006 | — | Nov 2007 | North Hertfordshire | 3.4 |
| Weston Hillswind farm | wind farm | 6 | refusedupdated Sep 2011 | Sep 2008 | refused Apr 2009 | Sep 2011 | North Hertfordshire | 4.9 |
| Westfield Conservation Parkbattery storage | battery storage | 99 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | North Hertfordshire | 5.4 |
| Langford Solar Farmsolar farm | solar farm | 13 | operationalupdated Apr 2015 | Jun 2013 | granted Sep 2013 | Apr 2015 | Central Bedfordshire | 6.7 |
| Langford Wind Farmwind farm | wind farm | 20 | operationalupdated Sep 2014 | Feb 2009 | granted Jan 2012 | Sep 2014 | Central Bedfordshire | 7.7 |
| Wymondley Solar Farm, Great Wymondleysolar farm | solar farm | 50 | approved, not builtupdated Feb 2026 | Dec 2021 | — | Feb 2026 | North Hertfordshire | 8.2 |
| Highfield Wind Farmwind farm | wind farm | 12.5 | appeal withdrawnupdated Sep 2014 | Mar 2012 | refused Feb 2014 | Sep 2014 | South Cambridgeshire | 8.3 |
| Dunton Lanebattery storage | battery storage | 200 | approved, not builtupdated Aug 2025 | Nov 2024 | granted Jul 2025 | Aug 2025 | Central Bedfordshire | 8.6 |
| Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm | solar farm | 18 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Aug 2023 | Feb 2026 | South Cambridgeshire | 8.7 |
| Highfield Farm, Royston Road Solar Farm & Battery Storagebattery storage | battery storage | 4.5 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Aug 2023 | Feb 2026 | South Cambridgeshire | 8.7 |
| Dunton Lanebattery storage | battery storage | 177 | approved, not builtupdated Nov 2025 | Feb 2025 | granted Oct 2025 | Nov 2025 | Central Bedfordshire | 9.2 |
| Solar Panels at Nw/O Cottered & Sw/O The A507 Cotteredbattery storage | battery storage | 354 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | East Hertfordshire | 9.5 |
| Solar Panels at Nw/O Cottered & Sw/O The A507 Cotteredsolar farm | solar farm | 49.9 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | East Hertfordshire | 9.5 |
| Stevenage Road, Titmore Greenbattery storage | battery storage | 57 | application submittedupdated Aug 2025 | May 2025 | — | Aug 2025 | North Hertfordshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Newnham Road, Newnhambattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Dec 2024 | granted Jun 2025 | Jul 2025 | North Hertfordshire | 1.4 |
| Chesfield Downs Golf Club, Jacks Hillrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | North Hertfordshire | 6.4 |
| Wymondley Solar Farm, Great Wymondleybattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Dec 2021 | — | Feb 2026 | North Hertfordshire | 8.2 |
| Eyeworth Lodge Farm, Eyeworthwind turbine | wind turbine | 0.2 | approved, not builtupdated Apr 2025 | Jun 2024 | granted Mar 2025 | Apr 2025 | Central Bedfordshire | 8.5 |
| Endoline Machinery Limited, Stratton Business Parkrooftop solar | rooftop solar | 0.7 | application withdrawnupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Central Bedfordshire | 9.0 |
| Stratton Business Park, Pegasus Driverooftop solar | rooftop solar | — | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Central Bedfordshire | 9.0 |
| Aco Technologies Plc, Hitchin Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Dec 2025 | Dec 2025 | Central Bedfordshire | 9.6 |
| Sainsburys, Hitchin Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Stevenage | 9.8 |
Distance from the average position of the SG7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 3 | 1 | 0 | 158 |
| Rooftop solar | 5 | 0 | 4 | 0 | 0 | 0.8 |
| Wind farm | 4 | 0 | 0 | 1 | 1 | 0 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Battery storage | 10 | 3 | 7 | 0 | 0 | 904 |
MW in pipeline: pending, approved and under-construction capacity.
How North Hertfordshire decides solar, wind and battery applications
| Applications | North Hertfordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 5 (29%) | 19% |
| Solar refused | 3 of 9 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 88.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
All projects in North Hertfordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.