Highfield Farm, Royston Road Solar Farm & Battery Storage (18 MW)

Highfield Farm, Royston Road Solar Farm & Battery Storage is an 18 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 August 2023, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
5 April 2023Application submitted
3 August 2023Planning permission granted

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Grupotec Solar 3 UK Limited
Planning authority
South Cambridgeshire
Planning application reference
23/01317/FUL
Site area
34.5 ha
Address (REPD)
Highfield Farm, Royston Road, Litlington
Council area (by location)
South Cambridgeshire
Time to decision
17 weeks
Contracts for Difference
AR7a
Name in REPD
Highfield Farm, Royston Road - Solar Farm & Battery Storage
REPD reference
13004

The scheme also includes 4.5 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfield Wind Farmwind farm12.5appeal withdrawn1.6
Bassingbourn Solar Farmsolar farm14.4operational3.0
Royston Solar Farm (Phase 1) (a)solar farm5operational3.7
Royston Solar Farm (Phase 1)solar farm5permission expired3.7
Munceys Farmsolar farm31.6operational5.7
Wisbridge Farmsolar farm9.3operational5.9
Bury Lane Fruit Farmsolar farm24operational5.9
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted5.9
Vine Farm Solar Parksolar farm45operational7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0484, -0.0686).