Energy Projects Near You

River Mel Solar Farm & Battery Storage System (25 MW)

River Mel Solar Farm & Battery Storage System is a 25 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 23 July 2025, no decision recorded; the record was last updated on 29 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
application submittedstatus in REPD
29 August 2025record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
23 July 2025Application submitted

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
application submitted
Record last updated
29 August 2025
Operator or applicant
Quintas Cleantech
Planning authority
South Cambridgeshire
Planning application reference
25/02739/FUL
Site area
50.1 ha
Address (REPD)
South Of Munceys Farm London Way Melbourn
Council area (by location)
South Cambridgeshire
Name in REPD
River Mel Solar Farm & Battery Storage System
REPD reference
17887

The scheme also includes 25 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bury Lane Fruit Farmsolar farm24operational0.8
Munceys Farmsolar farm31.6operational1.0
Royston Solar Farm (Phase 1)solar farm5permission expired2.3
Royston Solar Farm (Phase 1) (a)solar farm5operational2.3
Black Peak Farmsolar farm31.8operational2.8
Bassingbourn Solar Farmsolar farm14.4operational3.5
Hoback Farmsolar farm13.1operational5.7
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm18approved, not built5.9
Vine Farm Solar Parksolar farm45operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0734, 0.0083).