Energy Projects Near You

Solar, wind and battery projects near Royston (SG8)

23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SG8 (South Cambridgeshire): 2 are waiting for a planning decision, 5 approved but not yet running, 11 operational. The largest live scheme is River Mel Solar Farm & Battery Storage System (25 MW solar farm, application submitted on 23 July 2025, no decision recorded), 1.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23projects within 10 km
2awaiting a decision
5approved, not running
11operational

Projects within 10 km of SG8

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Royston Solar Farm (Phase 1) (a)solar farmsolar farm5operationalupdated Mar 2015Jul 2014granted Oct 2014Mar 2015North Hertfordshire0.5
Royston Solar Farm (Phase 1)solar farmsolar farm5permission expiredupdated Nov 2017Jul 2014granted Oct 2014Nov 2017North Hertfordshire0.5
Royston Solar Farm (Phase 2)solar farmsolar farm4permission expiredupdated Nov 2017Jul 2014granted Oct 2014Nov 2017North Hertfordshire0.5
Munceys Farmsolar farmsolar farm31.6operationalupdated May 2015Aug 2014granted Nov 2014May 2015South Cambridgeshire1.8
River Mel Solar Farm & Battery Storage Systemsolar farmsolar farm25application submittedupdated Aug 2025Jul 2025—Aug 2025South Cambridgeshire1.9
River Mel Solar Farm & Battery Storage Systembattery storagebattery storage25application submittedupdated Aug 2025Jul 2025—Aug 2025South Cambridgeshire1.9
Bassingbourn Solar Farmsolar farmsolar farm14.4operationalupdated Apr 2015Jan 2014granted Aug 2014Apr 2015South Cambridgeshire2.0
Bury Lane Fruit Farmsolar farmsolar farm24operationalupdated Feb 2017Dec 2013granted May 2014Feb 2017South Cambridgeshire2.0
Bassingbourn Barracks, Old North Road Solar PV Arrayssolar farmsolar farm2.3approved, not builtupdated Aug 2024Feb 2024granted Jul 2024Aug 2024South Cambridgeshire3.8
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farmsolar farm18approved, not builtupdated Feb 2026Apr 2023granted Aug 2023Feb 2026South Cambridgeshire4.1
Highfield Farm, Royston Road Solar Farm & Battery Storagebattery storagebattery storage4.5approved, not builtupdated Feb 2026Apr 2023granted Aug 2023Feb 2026South Cambridgeshire4.1
Black Peak Farmsolar farmsolar farm31.8operationalupdated May 2015Aug 2014granted Dec 2014May 2015South Cambridgeshire4.6
Hatch Penn Farm PVsolar farmsolar farm1operationalupdated Aug 2014Nov 2013granted Dec 2013Aug 2014North Hertfordshire4.8
Highfield Wind Farmwind farmwind farm12.5appeal withdrawnupdated Sep 2014Mar 2012refused Feb 2014Sep 2014South Cambridgeshire5.1
Hoback Farmsolar farmsolar farm13.1operationalupdated Nov 2014Feb 2013granted Jul 2013Nov 2014South Cambridgeshire6.2
Wisbridge Farmsolar farmsolar farm9.3operationalupdated Nov 2014Oct 2012granted Mar 2013Nov 2014North Hertfordshire6.3
Vine Farm Solar Parksolar farmsolar farm45operationalupdated Feb 2017May 2014—Feb 2017South Cambridgeshire6.4
Croydon Solar Farmsolar farmsolar farm5application withdrawnupdated Aug 2011Feb 2011—Aug 2011South Cambridgeshire7.2
Croydon / Church Farm (Royston)solar farmsolar farm16.5operationalupdated Apr 2015Oct 2013granted Aug 2014Apr 2015South Cambridgeshire8.4
Manor Farmsolar farmsolar farm14refusedupdated Oct 2014Aug 2014refused Jan 2015Oct 2014South Cambridgeshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Malton Golf Club, Malton Roadrooftop solarrooftop solar0.4approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026South Cambridgeshire5.9
South Farm, Shingay Cum Wendy - Ground Mounted Solar Arraysolar farmsolar farm0.2approved, not builtupdated Jun 2025Oct 2024granted Jun 2025Jun 2025South Cambridgeshire6.6
Lamp Hill Wimpole Estatesolar farmsolar farm0.4operationalupdated Feb 2020Feb 2019—Feb 2020South Cambridgeshire8.0

Distance from the average position of the SG8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm191311145.5
Rooftop solar101000.4
Wind farm100000
Battery storage2110029.5

MW in pipeline: pending, approved and under-construction capacity.

How South Cambridgeshire decides solar, wind and battery applications

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in South Cambridgeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.