Croydon Solar Farm (5 MW)

Croydon Solar Farm is a 5 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 21 June 2011; the record was last updated on 9 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
application withdrawnstatus in REPD
9 August 2011record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
23 February 2011Application submitted
21 June 2011Application withdrawn

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
application withdrawn
Record last updated
9 August 2011
Operator or applicant
Vogt Solar
Planning authority
South Cambridgeshire
Planning application reference
S/0319/11
Site area
14.2 ha
Address (REPD)
Land at Valley Farm, South Of Lower Road, Croydon, Cambridgeshire
Council area (by location)
South Cambridgeshire
REPD reference
1472

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Vine Farm Solar Parksolar farm45operational0.9
Croydon / Church Farm (Royston)solar farm16.5operational1.2
Hoback Farmsolar farm13.1operational3.0
Bassingbourn Solar Farmsolar farm14.4operational5.8
Bury Lane Fruit Farmsolar farm24operational6.7
Royston Solar Farm (Phase 1)solar farm5permission expired6.9
Royston Solar Farm (Phase 1) (a)solar farm5operational6.9
Highfield Wind Farmwind farm12.5appeal withdrawn7.0
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1187, -0.0732).