Croydon / Church Farm (Royston) (16.5 MW solar farm)

Croydon / Church Farm (Royston) is a 16.5 MW solar farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 27 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.5 MWsolar farm
operationalstatus in REPD
27 April 2015record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
31 October 2013Application submitted
1 August 2014Planning permission granted
20 January 2015Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
16.5 MW
Status (REPD)
operational
Record last updated
27 April 2015
Operator or applicant
Push Energy/ NextEnergy Solar Fund (NESF)
Planning authority
South Cambridgeshire
Planning application reference
S/2293/13/FL
Site area
34.6 ha
Address (REPD)
Church Farm, Church Lane, Croydon, Royston, Hertfordshire
Council area (by location)
South Cambridgeshire
Time to decision
39 weeks
REPD reference
1919

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Croydon Solar Farmsolar farm5application withdrawn1.2
Vine Farm Solar Parksolar farm45operational2.1
Hoback Farmsolar farm13.1operational3.6
Bassingbourn Solar Farmsolar farm14.4operational7.0
Bury Lane Fruit Farmsolar farm24operational7.8
Highfield Wind Farmwind farm12.5appeal withdrawn8.0
Royston Solar Farm (Phase 1) (a)solar farm5operational8.1
Royston Solar Farm (Phase 1)solar farm5permission expired8.1
Skylark Meadow Solar parksolar farm5operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1285, -0.0797).