Highfield Wind Farm (12.5 MW)

Highfield Wind Farm is a 12.5 MW wind farm project in South Cambridgeshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 5 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
appeal withdrawnstatus in REPD
5 September 2014record last updated
South Cambridgeshirecouncil area

Planning timeline

DateStage
12 March 2012Application submitted
19 February 2014Refused by the planning authority
2 September 2014Appeal withdrawn

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
appeal withdrawn
Record last updated
5 September 2014
Operator or applicant
Highfield Wind Energy Limited
Planning authority
South Cambridgeshire
Planning application reference
S/0439/12/FL
Turbines
5
Address (REPD)
Farmland South Of Litlington, South Camb, Royston, Hertfordshire
Council area (by location)
South Cambridgeshire
Time to decision
101 weeks
REPD reference
4380

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm18approved, not built1.6
Bassingbourn Solar Farmsolar farm14.4operational3.5
Royston Solar Farm (Phase 1) (a)solar farm5operational4.6
Royston Solar Farm (Phase 1)solar farm5permission expired4.6
Vine Farm Solar Parksolar farm45operational6.2
Bury Lane Fruit Farmsolar farm24operational6.7
Munceys Farmsolar farm31.6operational6.8
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted6.8
Tophams Solar Farmsolar farm40approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0564, -0.0878).