Energy Projects Near You

Tophams Solar Farm (40 MW)

Tophams Solar Farm is a 40 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 June 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
5 April 2022Application submitted
17 June 2024Planning permission granted
17 June 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
North Hertfordshire
Planning application reference
22/00741/FP
Site area
53.6 ha
Address (REPD)
W/O Ashwell Road, Bygrave, Baldock
Council area (by location)
North Hertfordshire
Time to decision
115 weeks
Contracts for Difference
AR7a
REPD reference
9037

The scheme also includes 8 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westonwind farm6application withdrawn4.5
Letchworth Garden City - Urban Reserve Energy Storage Facilitybattery storage5approved, not built4.7
Weston Hillswind farm6refused5.7
Westfield Conservation Parkbattery storage99application submitted5.7
Highfield Wind Farmwind farm12.5appeal withdrawn7.0
Langford Solar Farmsolar farm13operational7.1
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm18approved, not built7.5
Langford Wind Farmwind farm20operational7.8
Dunton Lanebattery storage200approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0125, -0.1607).