Westfield Conservation Park (99 MW battery storage)

Westfield Conservation Park is a 99 MW battery storage project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 5 August 2025, no decision recorded; the record was last updated on 28 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
application submittedstatus in REPD
28 October 2025record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
5 August 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
application submitted
Record last updated
28 October 2025
Operator or applicant
Lightrock Power Limited
Planning authority
North Hertfordshire
Planning application reference
25/01947/FP
Address (REPD)
S/O A507 At Westfield Common, Clothall Road, Clothall
Council area (by location)
North Hertfordshire
Name in REPD
Westfield Conservation Park - Battery Energy Storage System
REPD reference
19668

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Weston Hillswind farm6refused2.2
Westonwind farm6application withdrawn3.8
Solar Panels at Nw/O Cottered & Sw/O The A507 Cotteredsolar farm49.9application submitted4.5
Tophams Solar Farmsolar farm40approved, not built5.7
Letchworth Garden City - Urban Reserve Energy Storage Facilitybattery storage5approved, not built5.8
Wymondley Solar Farm, Great Wymondleysolar farm50approved, not built7.5
Benington Wind Farmwind farm6.8refused8.0
Stevenage Road, Titmore Greenbattery storage57application submitted8.5
Mill Farmsolar farm5operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9644, -0.1326).