Energy Projects Near You

Royston Solar Farm (Phase 1) (a) (5 MW)

Royston Solar Farm (Phase 1) (a) is a 5 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 January 2016; the record was last updated on 4 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 March 2015record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
1 July 2014Application submitted
29 October 2014Planning permission granted
1 December 2015Construction started
29 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 March 2015
Operator or applicant
Canadian Solar
Planning authority
South Cambridgeshire
Planning application reference
S/1427/14/FL
Site area
26.2 ha
Address (REPD)
Land between Railway and Sewage Disposal Works, Royston Road, Melbourn, Cambridgeshire
Council area (by location)
North Hertfordshire
Time to decision
17 weeks
Contracts for Difference
AR1
REPD reference
2202

Who decides

ApplicationsSouth CambridgeshireUK
Decided applications (solar, wind, battery)4810,236
Refused10 (21%)19%
Solar refused6 of 4012%
Onshore wind refused4 of 545%
Battery storage refused0 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Royston Solar Farm (Phase 1)solar farm5permission expired<0.1
Bassingbourn Solar Farmsolar farm14.4operational1.5
Munceys Farmsolar farm31.6operational2.3
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted2.3
Bury Lane Fruit Farmsolar farm24operational2.3
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm18approved, not built3.7
Highfield Wind Farmwind farm12.5appeal withdrawn4.6
Black Peak Farmsolar farm31.8operational5.1
Hoback Farmsolar farm13.1operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.065, -0.0223).