Wisbridge Farm (9.3 MW solar farm)

Wisbridge Farm is a 9.3 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2014; the record was last updated on 27 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.3 MWsolar farm
operationalstatus in REPD
27 November 2014record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
23 October 2012Application submitted
27 March 2013Planning permission granted
1 July 2014Construction started
1 October 2014Operational

Project details

Technology
solar farm
Capacity
9.3 MW
Status (REPD)
operational
Record last updated
27 November 2014
Operator or applicant
Push Energy
Planning authority
North Hertfordshire
Planning application reference
12/02365/1
Address (REPD)
High Street, Reed, Royston
Council area (by location)
North Hertfordshire
Time to decision
22 weeks
REPD reference
1940

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfield Farm, Royston Road Solar Farm & Battery Storagesolar farm18approved, not built5.9
Royston Solar Farm (Phase 1)solar farm5permission expired6.4
Royston Solar Farm (Phase 1) (a)solar farm5operational6.4
Munceys Farmsolar farm31.6operational6.5
Bassingbourn Solar Farmsolar farm14.4operational7.2
Highfield Wind Farmwind farm12.5appeal withdrawn7.4
River Mel Solar Farm & Battery Storage Systemsolar farm25application submitted7.4
Solar Panels at Nw/O Cottered & Sw/O The A507 Cotteredsolar farm49.9application submitted7.9
Bury Lane Fruit Farmsolar farm24operational8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.008, -0.0134).