Dunton Lane (177 MW battery storage)

Dunton Lane is a 177 MW battery storage project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 October 2025, not yet built; the record was last updated on 18 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

177 MWbattery storage
approved, not builtstatus in REPD
18 November 2025record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
11 February 2025Application submitted
24 October 2025Planning permission granted
24 October 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
177 MW
Status (REPD)
approved, not built
Record last updated
18 November 2025
Operator or applicant
Central Bedfordshire Council
Planning authority
Central Bedfordshire
Planning application reference
CB/25/00421/REG3
Address (REPD)
Dunton Lane, Biggleswade
Council area (by location)
Central Bedfordshire
Time to decision
36 weeks
Name in REPD
Dunton Lane - Battery Energy Storage System
REPD reference
17482

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunton Lanebattery storage200approved, not built0.8
Langford Wind Farmwind farm20operational2.7
Langford Solar Farmsolar farm13operational4.8
Lowfield Farm Solar Farmsolar farm26.5approved, not built6.5
Moggerhanger Road, Sandy Solar Farmsolar farm7application submitted7.3
Waterloo solar parksolar farm14.6operational7.8
Tophams Solar Farmsolar farm40approved, not built8.9
Solar Farm & Battery Storage at N/O Northill Roadsolar farm49.9application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0811, -0.2288).