Solar, wind and battery projects near Sandy (SG19)
26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SG19 (Central Bedfordshire): 5 are waiting for a planning decision, 15 approved but not yet running, 3 operational. The largest live scheme is Dunton Lane (200 MW battery storage, approved on 21 July 2025, not yet built), 7.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SG19
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Waterloo solar parksolar farm | solar farm | 14.6 | operationalupdated May 2015 | Oct 2013 | granted Apr 2014 | May 2015 | Central Bedfordshire | 1.6 |
| Lowfield Farm Solar Farmsolar farm | solar farm | 26.5 | approved, not builtupdated Dec 2025 | Jan 2025 | granted Nov 2025 | Dec 2025 | Central Bedfordshire | 1.7 |
| Moggerhanger Road, Sandy Solar Farmbattery storage | battery storage | 20 | application submitted may be out of dateupdated Apr 2022 | Mar 2022 | — | Apr 2022 | Central Bedfordshire | 4.8 |
| Moggerhanger Road, Sandy Solar Farmsolar farm | solar farm | 7 | application submitted may be out of dateupdated Apr 2022 | Mar 2022 | — | Apr 2022 | Central Bedfordshire | 4.8 |
| Abbotsley Country Homes, Drewels Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Jan 2025 | Feb 2026 | Huntingdonshire | 6.1 |
| Abbotsley Country Homes, Drewels Lane Solar Farmbattery storage | battery storage | 6 | approved, not builtupdated Mar 2025 | Dec 2023 | granted Jan 2025 | Mar 2025 | Huntingdonshire | 6.1 |
| Dunton Lanebattery storage | battery storage | 177 | approved, not builtupdated Nov 2025 | Feb 2025 | granted Oct 2025 | Nov 2025 | Central Bedfordshire | 6.5 |
| Dunton Lanebattery storage | battery storage | 200 | approved, not builtupdated Aug 2025 | Nov 2024 | granted Jul 2025 | Aug 2025 | Central Bedfordshire | 7.3 |
| Caldecote Manor Farmsolar farm | solar farm | 5 | operationalupdated Mar 2016 | Sep 2014 | granted Jan 2015 | Mar 2016 | Huntingdonshire | 8.2 |
| Langford Wind Farmwind farm | wind farm | 20 | operationalupdated Sep 2014 | Feb 2009 | granted Jan 2012 | Sep 2014 | Central Bedfordshire | 9.0 |
| Solar Farm & Battery Storage at N/O Northill Roadsolar farm | solar farm | 49.9 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Bedford | 9.4 |
| Solar Farm & Battery Storage at N/O Northill Roadbattery storage | battery storage | 15 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Bedford | 9.4 |
| Weald Farm, Cambridge Road Solar Farm & Battery Storagebattery storage | battery storage | 50 | approved, not builtupdated Feb 2026 | Apr 2024 | granted May 2025 | Feb 2026 | Huntingdonshire | 9.8 |
| Weald Farm, Cambridge Road Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Apr 2024 | granted May 2025 | Feb 2026 | Huntingdonshire | 9.8 |
| Cobholden Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | May 2024 | granted Jan 2025 | Feb 2026 | Bedford | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Tesco Stores, New Roadrooftop solar | rooftop solar | 0.3 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Central Bedfordshire | 3.9 |
| Flamingo Flowerssolar farm | solar farm | 0.5 | application withdrawnupdated Jun 2020 | Nov 2019 | — | Jun 2020 | Central Bedfordshire | 4.6 |
| Sainsbury, Bells Brookrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Central Bedfordshire | 5.7 |
| G And M Growers, Hitchin Road Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 | Central Bedfordshire | 6.7 |
| Stratton Business Park, Pegasus Driverooftop solar | rooftop solar | — | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Central Bedfordshire | 7.2 |
| Endoline Machinery Limited, Stratton Business Parkrooftop solar | rooftop solar | 0.7 | application withdrawnupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Central Bedfordshire | 7.2 |
| Old Warden Park, Old Wardenrooftop solar | rooftop solar | 0.3 | application withdrawnupdated Dec 2023 | Oct 2023 | — | Dec 2023 | Central Bedfordshire | 8.0 |
| Old Warden Aerodrome, Old Warden Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 | Central Bedfordshire | 8.0 |
| Eyeworth Lodge Farm, Eyeworthwind turbine | wind turbine | 0.2 | approved, not builtupdated Apr 2025 | Jun 2024 | granted Mar 2025 | Apr 2025 | Central Bedfordshire | 8.1 |
| Chester Road, Colmworth Business Park Solar Panlesrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Mar 2023 | granted Apr 2023 | Jun 2023 | Huntingdonshire | 8.4 |
| Alpha Drive, Eaton Soconrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2026 | Sep 2025 | granted Jan 2026 | Mar 2026 | Huntingdonshire | 8.7 |
Distance from the average position of the SG19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 2 | 4 | 2 | 0 | 233 |
| Rooftop solar | 9 | 1 | 6 | 0 | 0 | 1.7 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Battery storage | 6 | 2 | 4 | 0 | 0 | 468 |
MW in pipeline: pending, approved and under-construction capacity.
How Central Bedfordshire decides solar, wind and battery applications
| Applications | Central Bedfordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 59 | 10,236 |
| Refused | 8 (14%) | 19% |
| Solar refused | 4 of 36 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Battery storage refused | 2 of 16 | 16% |
| Median time from submission to decision | 19.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
All projects in Central Bedfordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SG19, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.