East Park Energy (400 MW solar farm)

East Park Energy is a 400 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 30 October 2025, no decision recorded; the record was last updated on 1 May 2026. As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010141).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWsolar farm
application submittedstatus in REPD
1 May 2026record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
30 October 2025Application submitted

Project details

Technology
solar farm
Capacity
400 MW
Status (REPD)
application submitted
Record last updated
1 May 2026
Operator or applicant
Brockwell Energy
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010141
Site area
773.0 ha
Address (REPD)
E/O Little Staughton, Btw S/O Great Staughton, Kimbolton Road, Hail Weston, St Neots
Council area (by location)
Huntingdonshire
REPD reference
15347

The scheme also includes 100 MW of battery storage, recorded separately in REPD (application submitted).

Official project record at the Planning Inspectorate (EN010141)

Who decides

As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010141). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cobholden Solar Farmsolar farm49.9approved, not built3.4
Common Barn Wind Farmwind farm6.2operational3.6
Staughton Airfield Solar Farmsolar farm40operational4.2
Vicarage Lane, Diddington Solar Arrayssolar farm35application submitted4.6
Cobholden Battery Storagebattery storage100approved, not built5.4
Abbotsley Country Homes, Drewels Lane Solar Farmsolar farm49.9approved, not built6.9
Weald Farm, Cambridge Road Solar Farm & Battery Storagesolar farm49.9approved, not built7.2
Cotton Farmwind farm20operational7.2
Caldecote Manor Farmsolar farm5operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.246, -0.2978).