Abbey Farm (9 MW solar farm)

Abbey Farm is a 9 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2014; the record was last updated on 3 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
operationalstatus in REPD
3 April 2014record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
15 January 2013Application submitted
5 September 2013Planning permission granted
19 March 2014Operational

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
3 April 2014
Operator or applicant
Anesco
Planning authority
Huntingdonshire
Planning application reference
1202026FUL
Site area
20.1 ha
Address (REPD)
Double Bank Lane, Sawtry, Huntingdon, Cambridgeshire, PE28 5YJ
Council area (by location)
Huntingdonshire
Time to decision
33 weeks
REPD reference
1737

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Red House Farm Solar Farmsolar farm20approved, not built0.5
Abbots Ripton Solar Farmsolar farm24.7operational5.2
Land at Biggin Lanesolar farm5operational7.6
Bury Green Farm Solarsolar farm5operational7.6
Little Staughton Solar Farmsolar farm50approved, not built9.3
Ramsey Wind Farm Extensionwind farm8operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4193, -0.2366).