Energy Projects Near You

Ramsey Wind Farm Extension (8 MW)

Ramsey Wind Farm Extension is an 8 MW wind farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 April 2015; the record was last updated on 24 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
operationalstatus in REPD
24 April 2015record last updated
Huntingdonshirecouncil area

Planning timeline

DateStage
8 November 2011Application submitted
22 May 2013Planning permission granted
1 November 2014Construction started
23 April 2015Operational

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
24 April 2015
Operator or applicant
REG Windpower
Planning authority
Huntingdonshire
Planning application reference
1101865FUL
Turbines
4
Address (REPD)
St Marys Road, Ramsey
Council area (by location)
Huntingdonshire
Time to decision
80 weeks
REPD reference
4414

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bury Green Farm Solarsolar farm5operational2.1
Little Staughton Solar Farmsolar farm50approved, not built2.4
Land at Biggin Lanesolar farm5operational2.7
Glass Moorwind farm16operational5.7
Glass moor Extensionwind farm12operational5.7
Red Tilewind farm24operational7.6
Haddon Solar parksolar farm22refused8.0
Red House Farm Solar Farmsolar farm20approved, not built9.1
Abbey Farmsolar farm9operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4681, -0.1224).