Energy Projects Near You

Red House Farm Solar Farm (20 MW)

Red House Farm Solar Farm is a 20 MW solar farm project in Huntingdonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 December 2021, not yet built; the record was last updated on 14 December 2021. REPD records the planning permission as expiring on 7 December 2024, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtmay be out of datestatus in REPD
14 December 2021record last updated
Huntingdonshirecouncil area

REPD records the planning permission as expiring on 7 December 2024, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
4 August 2021Application submitted
7 December 2021Planning permission granted
7 December 2024Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
14 December 2021
Operator or applicant
Anesco Limited
Planning authority
Huntingdonshire
Planning application reference
21/01809/FUL
Site area
24.1 ha
Address (REPD)
Nw/O Red House Farm On Double, Bank Lane, Sawtry, Huntingdon
Council area (by location)
Huntingdonshire
Time to decision
18 weeks
Contracts for Difference
AR6
Name in REPD
Red House Farm - Solar Farm
REPD reference
9518

Who decides

ApplicationsHuntingdonshireUK
Decided applications (solar, wind, battery)4710,236
Refused7 (15%)19%
Solar refused1 of 3312%
Onshore wind refused6 of 1145%
Battery storage refused0 of 316%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abbey Farmsolar farm9operational0.5
Abbots Ripton Solar Farmsolar farm24.7operational4.8
Land at Biggin Lanesolar farm5operational7.2
Bury Green Farm Solarsolar farm5operational7.3
Little Staughton Solar Farmsolar farm50approved, not built8.9
Ramsey Wind Farm Extensionwind farm8operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4178, -0.2291).