Energy Projects Near You

Solar, wind and battery projects near Chatteris (PE16)

20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE16 (Fenland): 7 approved but not yet running, 9 operational. The largest live scheme is Bartlett Business Park (2.1 MW rooftop solar, approved on 5 May 2026, not yet built), 0.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects within 10 km
0awaiting a decision
7approved, not running
9operational

Projects within 10 km of PE16

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bartlett Business Parkrooftop solarrooftop solar2.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Fenland0.5
Land East Of Honeysome Roadsolar farmsolar farm4.6operationalupdated Apr 2016May 2015granted Dec 2015Apr 2016Fenland0.7
Alan Bartlett & Sons Solarrooftop solarrooftop solar1.2operationalupdated Oct 2013——Oct 2013Fenland0.9
Honey Hillwind farmwind farm2application withdrawnupdated Apr 2006Aug 1999—Apr 2006Fenland5.9
Red Tilewind farmwind farm24operationalupdated Dec 2017Oct 2003granted Feb 2005Dec 2017Huntingdonshire6.0
Ranson Moor Wind Farm (Phase 2)wind farmwind farm4operationalupdated Jun 2018May 2006granted Feb 2007Jun 2018Fenland6.2
Ranson Moor (phase 1)wind farmwind farm6operationalupdated May 2009Jul 2003granted Apr 2005May 2009Fenland6.5
Floods Ferry Farmwind farmwind farm18refused on appealupdated Jan 2012Apr 2009refused Jan 2010Jan 2012Fenland7.9
Greenvale AP Wind Turbinewind turbinewind turbine1.5operationalupdated Apr 2016Jul 2012granted Sep 2012Apr 2016Fenland8.1
Knights End Road Solar Farmsolar farmsolar farm5permission expiredupdated Jan 2020Oct 2015granted Dec 2015Jan 2020Fenland8.9
Boardinghouse Wind Farmwind farmwind farm10.3operationalupdated Dec 2015Aug 2009granted Jul 2011Dec 2015Fenland8.9
Turves/Burtnhouse Solar Farm Extensionsolar farmsolar farm4.7operationalupdated Jan 2015Apr 2014granted Jul 2014Jan 2015Fenland9.7
Turves Solar Farmsolar farmsolar farm5operationalupdated Apr 2013May 2011granted Apr 2012Apr 2013Fenland9.8
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Colne Fen Farm, Chatteris Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Huntingdonshire4.2
Asksham Community Village Solar Farmsolar farmsolar farm0.1under constructionupdated Jan 2022Oct 2020granted Feb 2021Jan 2022Fenland5.1
Arthur Rickwood Farm, Chatteris Roadsolar farmsolar farm0.7application withdrawnupdated Sep 2023Apr 2023—Sep 2023East Cambridgeshire5.5
Lees Packhouse, The Gaultrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023East Cambridgeshire5.9
Tick Fen Farm, Puddock Roadwind turbinewind turbine0.5approved, not builtupdated Jul 2024Mar 2024granted May 2024Jul 2024Huntingdonshire7.1
Tick Fen Farm, Puddock Roadwind turbinewind turbine0.5approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Huntingdonshire7.2
Linwood Farm, Linwood Lanerooftop solarrooftop solar0.4approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Fenland7.8

Distance from the average position of the PE16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm601300.1
Rooftop solar504103.3
Wind farm600410
Wind turbine302101

MW in pipeline: pending, approved and under-construction capacity.

How Fenland decides solar, wind and battery applications

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in Fenland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.