Solar, wind and battery projects near March (PE15)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE15 (Fenland): 3 are waiting for a planning decision, 6 approved but not yet running, 16 operational. The largest live scheme is West Fen Farm, Whitemoor Road Solar Farm (49.8 MW solar farm, application submitted on 30 May 2025, no decision recorded), 4.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PE15
Projects of 1 MW and more (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Boardinghouse Wind Farmwind farm | wind farm | 10.3 | operationalupdated Dec 2015 | Aug 2009 | granted Jul 2011 | Dec 2015 | Fenland | 1.7 |
| West Fen Farm, Whitemoor Road Solar Farmsolar farm | solar farm | 49.8 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Fenland | 4.0 |
| West Fen Farm, Whitemoor Roadbattery storage | battery storage | 30 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Fenland | 4.0 |
| Long Hill Roadwind turbine | wind turbine | 2 | operationalupdated Apr 2009 | Jul 2001 | granted Apr 2003 | Apr 2009 | Fenland | 4.0 |
| Stags Holtwind farm | wind farm | 18 | operationalupdated May 2009 | Dec 2001 | granted May 2002 | May 2009 | Fenland | 4.4 |
| Stags Holt Extensionwind turbine | wind turbine | 2 | operationalupdated Jul 2013 | Jun 2007 | granted Oct 2008 | Jul 2013 | Fenland | 4.4 |
| Ranson Moor Wind Farm (Phase 2)wind farm | wind farm | 4 | operationalupdated Jun 2018 | May 2006 | granted Feb 2007 | Jun 2018 | Fenland | 4.4 |
| March Sewage Treatment Workswind turbine | wind turbine | 2 | operationalupdated Apr 2013 | Jul 2007 | granted Feb 2009 | Apr 2013 | Fenland | 4.5 |
| Knights End Road Solar Farmsolar farm | solar farm | 5 | permission expiredupdated Jan 2020 | Oct 2015 | granted Dec 2015 | Jan 2020 | Fenland | 4.5 |
| Ranson Moor (phase 1)wind farm | wind farm | 6 | operationalupdated May 2009 | Jul 2003 | granted Apr 2005 | May 2009 | Fenland | 4.6 |
| Floods Ferry Farmwind farm | wind farm | 18 | refused on appealupdated Jan 2012 | Apr 2009 | refused Jan 2010 | Jan 2012 | Fenland | 6.3 |
| Greenvale AP Wind Turbinewind turbine | wind turbine | 1.5 | operationalupdated Apr 2016 | Jul 2012 | granted Sep 2012 | Apr 2016 | Fenland | 6.4 |
| Coldhamwind farm | wind farm | 16 | operationalupdated Apr 2011 | Aug 1999 | granted Oct 2004 | Apr 2011 | Fenland | 6.7 |
| Whitemill Wind Farmwind farm | wind farm | 14 | operationalupdated Aug 2012 | Nov 2007 | granted Nov 2008 | Aug 2012 | Fenland | 7.2 |
| Coldham Estate Solar Farmsolar farm | solar farm | 10 | permission expiredupdated Oct 2020 | Sep 2019 | granted Dec 2019 | Oct 2020 | Fenland | 7.2 |
| Coldham Estate Solar Farmbattery storage | battery storage | 6 | permission expiredupdated Dec 2019 | Sep 2019 | granted Dec 2021 | Dec 2019 | Fenland | 7.2 |
| Coldham Hallwind farm | wind farm | 14 | operationalupdated May 2009 | Jan 2002 | granted Oct 2002 | May 2009 | Fenland | 7.5 |
| Turves Solar Farmsolar farm | solar farm | 5 | operationalupdated Apr 2013 | May 2011 | granted Apr 2012 | Apr 2013 | Fenland | 7.6 |
| Turves/Burtnhouse Solar Farm Extensionsolar farm | solar farm | 4.7 | operationalupdated Jan 2015 | Apr 2014 | granted Jul 2014 | Jan 2015 | Fenland | 7.6 |
| Darcey Lodewind farm | wind farm | 2 | application withdrawnupdated Nov 2005 | Aug 1999 | — | Nov 2005 | Fenland | 7.8 |
| Burnt House Farmwind farm | wind farm | 6 | operationalupdated Jun 2013 | Jun 2009 | granted Jul 2011 | Jun 2013 | Fenland | 8.1 |
| Honey Hillwind farm | wind farm | 2 | application withdrawnupdated Apr 2006 | Aug 1999 | — | Apr 2006 | Fenland | 8.2 |
| Willow Farmsolar farm | solar farm | 1.1 | operationalupdated Aug 2022 | Jan 2021 | granted Nov 2021 | Aug 2022 | Fenland | 9.2 |
| Land East Of Honeysome Roadsolar farm | solar farm | 4.6 | operationalupdated Apr 2016 | May 2015 | granted Dec 2015 | Apr 2016 | Fenland | 9.5 |
| Bartlett Business Parkrooftop solar | rooftop solar | 2.1 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Fenland | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Linwood Farm, Linwood Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Fenland | 1.7 |
| Hostmoor Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Fenland | 2.9 |
| Tesco Stores, Hostmoor Avenuerooftop solar | rooftop solar | 0.4 | application submitted | May 2026 | — | — | Fenland | 2.9 |
| Storelogs Holdings, Marwick Roadsolar farm | solar farm | 0.6 | approved, not builtupdated May 2025 | Mar 2025 | granted May 2025 | May 2025 | Fenland | 3.2 |
| Storelogs Holdings, Marwick Roadsolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Oct 2024 | Nov 2024 | Fenland | 3.2 |
| Asksham Community Village Solar Farmsolar farm | solar farm | 0.1 | under constructionupdated Jan 2022 | Oct 2020 | granted Feb 2021 | Jan 2022 | Fenland | 4.7 |
Distance from the average position of the PE15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 1 | 3 | 4 | 0 | 50.8 |
| Rooftop solar | 4 | 1 | 3 | 0 | 0 | 3.6 |
| Wind farm | 11 | 0 | 0 | 8 | 1 | 0 |
| Wind turbine | 4 | 0 | 0 | 4 | 0 | 0 |
| Battery storage | 2 | 1 | 0 | 0 | 0 | 30 |
MW in pipeline: pending, approved and under-construction capacity.
How Fenland decides solar, wind and battery applications
| Applications | Fenland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 10 (20%) | 19% |
| Solar refused | 3 of 23 | 12% |
| Onshore wind refused | 6 of 21 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 23.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.