Energy Projects Near You

Turves Solar Farm (5 MW)

Turves Solar Farm is a 5 MW solar farm project in Fenland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2013; the record was last updated on 12 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
12 April 2013record last updated
Fenlandcouncil area

Planning timeline

DateStage
13 May 2011Application submitted
12 April 2012Planning permission granted
2 November 2012Construction started
19 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
12 April 2013
Operator or applicant
Abbey Renewables
Planning authority
Fenland
Planning application reference
F/YR11/0362/F
Address (REPD)
Land West Of 15 Burnthouse Sidings, Turves, Whittlesey,
Council area (by location)
Fenland
Time to decision
48 weeks
REPD reference
1171

Earlier applications for this site

ApplicationMWSubmittedOutcome
Turves Solar Farm F/YR11/0020/F520 December 2010refused 21 March 2011

Who decides

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burnt House Farmwind farm6operational0.9
Floods Ferry Farmwind farm18refused on appeal2.0
Knights End Road Solar Farmsolar farm5permission expired3.1
Ranson Moor (phase 1)wind farm6operational4.4
Glass moor Extensionwind farm12operational5.7
Glass Moorwind farm16operational5.7
Boardinghouse Wind Farmwind farm10.3operational5.9
West Fen Farm, Whitemoor Road Solar Farmsolar farm49.8application submitted6.1
West Fen Farm, Whitemoor Roadbattery storage30application submitted6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5303, -0.0262).