Energy Projects Near You

Solar, wind and battery projects near Wisbech (PE13)

43 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE13 (Fenland): 1 is waiting for a planning decision, 23 approved but not yet running, 7 operational. The largest live scheme is Lapwing Fen 2 Battery Storage Plant (250 MW battery storage, under construction since 1 June 2022), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43projects within 10 km
1awaiting a decision
23approved, not running
7operational

Projects within 10 km of PE13

Projects of 1 MW and more (30)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Walsoken, Burrettgate Roadbattery storagebattery storage200approved, not builtupdated Aug 2025Dec 2023granted Jul 2025Aug 2025King's Lynn and West Norfolk3.5
Wisbech Solar Farmsolar farmsolar farm3.5operationalupdated Mar 2016Oct 2014granted Jan 2015Mar 2016Fenland4.0
Tydd Solar Farmsolar farmsolar farm24.9refusedupdated Jun 2025Apr 2024refused May 2025Jun 2025Fenland4.4
Tydd Solar Farmbattery storagebattery storage15refusedupdated Jun 2025Apr 2024refused May 2025Jun 2025Fenland4.4
Tydd Solar Farmsolar farmsolar farm24.9refusedupdated Jul 2025May 2024refused Jun 2025Jul 2025Fenland4.4
Tydd Solar Farmbattery storagebattery storage15refusedupdated Jul 2025May 2024refused Jun 2025Jul 2025Fenland4.4
Delph Wind Farmwind farmwind farm27application withdrawnupdated Jul 2014Feb 2013—Jul 2014Fenland5.4
Treading Wind Farm - South Hollandwind farmwind farm5refusedupdated Oct 2013Feb 2011refused Sep 2012Oct 2013Fenland6.0
Meerdyke Solar Panels & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024King's Lynn and West Norfolk6.0
Rose And Crown Farmsolar farmsolar farm30operationalupdated Jun 2016Feb 2014granted Sep 2015Jun 2016King's Lynn and West Norfolk6.2
Lapwing Fen II, Crown Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Nov 2022Nov 2019granted Mar 2020Nov 2022Fenland6.4
Treading Wind Farm - Fenlandwind farmwind farm15refused on appealupdated Oct 2013Jan 2011refused Jul 2012Oct 2013Fenland6.6
Treading Bank Solar Farmsolar farmsolar farm49.9refusedupdated Dec 2025Oct 2025refused Dec 2025Dec 2025Fenland6.7
Lapwing Fen 2 Battery Storage Plantbattery storagebattery storage250under constructionupdated Jun 2022Nov 2019granted Apr 2020Jun 2022Fenland6.9
Walpole Banksolar farmsolar farm40under constructionupdated Nov 2024Sep 2020granted Jan 2021Nov 2024King's Lynn and West Norfolk7.2
Model Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Jan 2022Feb 2022King's Lynn and West Norfolk7.6
Coldham Hallwind farmwind farm14operationalupdated May 2009Jan 2002granted Oct 2002May 2009Fenland7.6
Walpole St Andrewbattery storagebattery storage100approved, not built may be out of dateupdated Jul 2024Feb 2022granted Sep 2022Jul 2024King's Lynn and West Norfolk7.7
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Jun 2026Dec 2022granted Jul 2023Jun 2026King's Lynn and West Norfolk7.7
Walpole Bankbattery storagebattery storage100application submitted may be out of dateupdated Apr 2023Nov 2022—Apr 2023King's Lynn and West Norfolk7.7
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Feb 2026Nov 2022granted Jul 2023Feb 2026King's Lynn and West Norfolk7.8
North Walpole, St Peterbattery storagebattery storage100approved, not built may be out of dateupdated Oct 2021Sep 2021granted Jun 2022Oct 2021King's Lynn and West Norfolk7.9
Coldham Estate Solar Farmsolar farmsolar farm10permission expiredupdated Oct 2020Sep 2019granted Dec 2019Oct 2020Fenland8.2
Coldham Estate Solar Farmbattery storagebattery storage6permission expiredupdated Dec 2019Sep 2019granted Dec 2021Dec 2019Fenland8.2
Gunthorpe Road, Marsh Solar Farmsolar farmsolar farm49.9approved, not builtupdated Jan 2024Jul 2021granted Sep 2023Jan 2024South Holland8.3
Coldhamwind farmwind farm16operationalupdated Apr 2011Aug 1999granted Oct 2004Apr 2011Fenland8.6
Whitemill Wind Farmwind farmwind farm14operationalupdated Aug 2012Nov 2007granted Nov 2008Aug 2012Fenland8.6
Fendyke Solar Farm - Extensionsolar farmsolar farm5refused on appealupdated Nov 2016Feb 2015refused Sep 2015Nov 2016South Holland9.1
The Grange Wind Farmwind farmwind farm14operationalupdated Apr 2013Jun 2009granted Oct 2010Apr 2013South Holland9.2
Marshlands Farmwind farmwind farm57application withdrawnupdated Jul 2009Oct 2008—Jul 2009King's Lynn and West Norfolk9.8
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cromwell Road Tescorooftop solarrooftop solar0.8approved, not builtupdated Sep 2023Jan 2020granted Mar 2020Sep 2023Fenland2.1
Boleness Roadrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Fenland2.6
Volmary Sitesolar farmsolar farm0.2operationalupdated Jul 2019Jan 2019granted Mar 2019Jul 2019Fenland2.9
Wisbech St Mary Sports & Community Centre Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Fenland3.0
Princes Truna Limited, Walsokenrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024King's Lynn and West Norfolk3.7
Fenmarc Produce, Gosmoor Lane Solar Farm & Battery Storagesolar farmsolar farm1approved, not builtupdated Oct 2023Apr 2023granted Oct 2023Oct 2023Fenland5.2
Fenmarc Produce, Gosmoor Lane Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Oct 2023Apr 2023granted Oct 2023Oct 2023Fenland5.2
Meerdyke Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024King's Lynn and West Norfolk6.0
Land Adjacent to Walpole National Grid Substationbattery storagebattery storage—approved, not builtupdated Dec 2025Aug 2024granted Nov 2025Dec 2025King's Lynn and West Norfolk8.0
Gunthorpe Road, Marsh -Battery Storagebattery storagebattery storage—approved, not builtupdated Oct 2024Jul 2021granted Feb 2022Oct 2024South Holland8.3
Askew And Barrett Pulses, Smeeth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023King's Lynn and West Norfolk8.8
Poplar Farm, Old Fendykerooftop solarrooftop solar0.7approved, not built may be out of dateupdated Aug 2023Jun 2023granted Jul 2023Aug 2023South Holland9.7
Poplar Farm, Old Fendykerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Aug 2023Jun 2023granted Jul 2023Aug 2023South Holland9.9

Distance from the average position of the PE13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm120434141
Rooftop solar606003.1
Wind farm800420
Battery storage17113021,050

MW in pipeline: pending, approved and under-construction capacity.

How Fenland decides solar, wind and battery applications

ApplicationsFenlandUK
Decided applications (solar, wind, battery)4910,236
Refused10 (20%)19%
Solar refused3 of 2312%
Onshore wind refused6 of 2145%
Battery storage refused1 of 516%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in Fenland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE13, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.