Energy Projects Near You

Model Farm (49.9 MW battery storage)

Model Farm is a 49.9 MW battery storage project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 January 2022, not yet built; the record was last updated on 24 February 2022. REPD also records that the planning permission expired on 27 January 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
24 February 2022record last updated
King's Lynn and West Norfolkcouncil area

REPD also records that the planning permission expired on 27 January 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
31 August 2021Application submitted
27 January 2022Planning permission granted
27 January 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
24 February 2022
Operator or applicant
Tribus Clean Energy
Planning authority
King's Lynn and West Norfolk
Planning application reference
21/01715/FM
Address (REPD)
Model Farm, Frenchs Road, Walpole St. Andrew, Wisbech,
Council area (by location)
King's Lynn and West Norfolk
Time to decision
21 weeks
REPD reference
10687

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Walpole Banksolar farm40under construction0.7
Walpole St Andrewbattery storage100approved, not built0.7
Walpole Sub Station, Walpole Bankbattery storage100approved, not built0.8
Walpole Sub Station, Walpole Bankbattery storage100approved, not built1.0
Walpole Bankbattery storage100application submitted1.2
Gunthorpe Road, Marsh Solar Farmsolar farm49.9approved, not built1.5
Lapwing Fen 2 Battery Storage Plantbattery storage250under construction1.6
Lapwing Fen II, Crown Farmbattery storage49.9approved, not built1.7
Rose And Crown Farmsolar farm30operational1.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7281, 0.1952).