Energy Projects Near You

Renewable energy projects in King's Lynn and West Norfolk

62 solar, wind or battery projects of 150 kW or more are located in King's Lynn and West Norfolk (REPD, July 2026 extract): 3 pending, 37 approved but not running, 13 operational and 2 refused. The council refused 11 of 60 decided applications (18%; UK 19%), with a median 14 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

62projects in the council area
3awaiting a decision
37approved, not running
18%of decisions refused

How King's Lynn and West Norfolk decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Projects in King's Lynn and West Norfolk

Projects of 1 MW and more (37)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Walsoken, Burrettgate Roadbattery storagebattery storage200approved, not builtupdated Aug 2025Dec 2023granted Jul 2025Aug 2025
North Walpole, St Peterbattery storagebattery storage100approved, not built may be out of dateupdated Oct 2021Sep 2021granted Jun 2022Oct 2021
Walpole St Andrewbattery storagebattery storage100approved, not built may be out of dateupdated Jul 2024Feb 2022granted Sep 2022Jul 2024
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Feb 2026Nov 2022granted Jul 2023Feb 2026
Walpole Sub Station, Walpole Bankbattery storagebattery storage100approved, not built may be out of dateupdated Jun 2026Dec 2022granted Jul 2023Jun 2026
Walpole Bankbattery storagebattery storage100application submitted may be out of dateupdated Apr 2023Nov 2022—Apr 2023
Marshlands Farmwind farmwind farm57application withdrawnupdated Jul 2009Oct 2008—Jul 2009
High Road, Saddlebowbattery storagebattery storage50approved, not builtupdated Aug 2024Jul 2022granted Jul 2024Aug 2024
Estuary Farm, Edward Benefer Way Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Dec 2021Jul 2021granted Dec 2021Dec 2021
Model Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Jan 2022Feb 2022
Meerdyke Solar Panels & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024
Walpole Banksolar farmsolar farm40under constructionupdated Nov 2024Sep 2020granted Jan 2021Nov 2024
Rose And Crown Farmsolar farmsolar farm30operationalupdated Jun 2016Feb 2014granted Sep 2015Jun 2016
South Creake Solar Farmsolar farmsolar farm26operationalupdated Aug 2016Mar 2013granted Jun 2013Aug 2016
Ongar Hill Wind Farmwind farmwind farm22refused on appealupdated Sep 2016Mar 2012refused Feb 2015Sep 2016
Sedgeford Hall Estate Solar Panels & Battery Storagesolar farmsolar farm21approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022
Thornham Solar Farmsolar farmsolar farm15abandonedupdated Apr 2015Jan 2013granted Apr 2013Apr 2015
Estuary Farm, Edward Benefer Way Solar Farm & Battery Storagebattery storagebattery storage15approved, not built may be out of dateupdated Dec 2021Jul 2021granted Dec 2021Dec 2021
Solar PV Panelssolar farmsolar farm15approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025
Jack's Lane Wind Farmwind farmwind farm13.8operationalupdated Nov 2016Aug 2010granted May 2012Nov 2016
Sedgefordwind farmwind farm10.8application withdrawnupdated Nov 2005——Nov 2005
Hall Farm, West End Northwold Solar Farmsolar farmsolar farm10operationalupdated Mar 2025Dec 2021granted Mar 2022Mar 2025
Chiplowwind farmwind farm8.2operationalupdated Aug 2016May 2010granted May 2012Aug 2016
Hall Farm, West End Northwold Solar Farmbattery storagebattery storage7.5operationalupdated Mar 2025Dec 2021granted Mar 2022Mar 2025
Reaches Farm Solar Parksolar farmsolar farm6.1operationalupdated May 2014May 2013granted Aug 2013May 2014
Meadow Farm solar parksolar farmsolar farm6operationalupdated Jul 2014May 2013granted Jul 2013Jul 2014
Jack's Lane Solarsolar farmsolar farm5permission expiredupdated Jun 2020Oct 2015granted Feb 2016Jun 2020
Ryston Estate Solar Parksolar farmsolar farm4.8operationalupdated Aug 2015May 2013granted Aug 2013Aug 2015
Snettisham Solar Farmsolar farmsolar farm2.5abandonedupdated Mar 2017Aug 2015granted Nov 2015Mar 2017
Sandringham Estatesolar farmsolar farm2.1approved, not builtupdated Jul 2024Apr 2024granted Jul 2024Jul 2024
Porvair International Ltdsolar farmsolar farm1.8operationalupdated Mar 2013Jan 2011granted Mar 2011Mar 2013
Choseley Farmwind farmwind farm1.8application withdrawnupdated Nov 2005——Nov 2005
K L Technologies Wind Turbinewind turbinewind turbine1.5operationalupdated Feb 2014Dec 2011granted Sep 2012Feb 2014
Pil Membranes, Estuary Roadwind turbinewind turbine1.5approved, not built may be out of dateupdated Mar 2023Sep 2022granted Mar 2023Mar 2023
Mickram Limitedsolarsolar1.4abandonedupdated Feb 2014Oct 2012granted Feb 2013Feb 2014
Chamber 16 (Cold Store)rooftop solarrooftop solar1.2operationalupdated Sep 2018Feb 2015granted Jun 2015Sep 2018
Field north of Water Treatment Works / Hoggs Drovesolar farmsolar farm1operationalupdated Oct 2022Oct 2018granted May 2021Oct 2022
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Alfred G Pearce, Castle Road Solar Farmsolar farmsolar farm0.7refusedupdated Apr 2024Nov 2022refused Mar 2024Apr 2024
Home Farm, Bircham Road Solar Arrayssolar farmsolar farm0.5approved, not builtupdated Jul 2026Mar 2026granted May 2026Jul 2026
Wm Morrisons- Solar Photovoltaic Systemrooftop solarrooftop solar0.5approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022
Lynn Road, Southeryrooftop solarrooftop solar0.5approved, not builtupdated Oct 2021Oct 2021granted Jan 2022Oct 2021
Princes Truna Limited, Walsokenrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Askew And Barrett Pulses, Smeeth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023
Southery Road Farm, Ploughmans Droverooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Sep 2024granted Oct 2024Oct 2024
Guy-Raymond Engineering Company, Rollesby Roadsolar farmsolar farm0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026
Former RAF Methwoldsolar farmsolar farm0.3application submitted may be out of dateupdated Jan 2021Sep 2020—Jan 2021
Optima Stainless Limited, Hamlin Wayrooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026
Towlers Farm, Southery Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025
The Laurels Farm, Ongar Hill Roadwind farmwind farm0.2approved, not builtupdated Jun 2026Jan 2026granted Apr 2026Jun 2026
Saddlebow Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023
Thetford Road, Pooly Farmsolar farmsolar farm0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025
Docking Lodge Farm, Docking Solar PV Systemsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025
Oldmedow Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022
Denver Complex, Sluice Roadfloating solarfloating solar0.2approved, not built may be out of dateupdated Mar 2023Dec 2022granted Mar 2023Mar 2023
Northfield Farm, Lynn Roadrooftop solarrooftop solar0.2application submittedMay 2026——
Sedgeford Hall Estate Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022
Meerdyke Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2024Nov 2022granted Mar 2024Mar 2024
Sandringham Estatebattery storagebattery storage—approved, not builtupdated Jul 2024Apr 2024granted Jul 2024Jul 2024
Land Adjacent to Walpole National Grid Substationbattery storagebattery storage—approved, not builtupdated Dec 2025Aug 2024granted Nov 2025Dec 2025
Long Acres Holiday Park, South Beach Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025
Sluice Road, Wiggenhall St Germans Solar Array & Battery Storagesolar farmsolar farm—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Sluice Road, Wiggenhall St Germans Solar Array & Battery Storagebattery storagebattery storage—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025

Postcode districts in King's Lynn and West Norfolk

DistrictProjects within 10 kmPendingApprovedOperational
IP2614355
PE14301179
PE30180123
PE3114072
PE3211225
PE335022
PE34311224
PE358060
PE367030
PE386131

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to King's Lynn and West Norfolk by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.