South Creake Solar Farm (26 MW)

South Creake Solar Farm is a 26 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 March 2016; the record was last updated on 18 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWsolar farm
operationalstatus in REPD
18 August 2016record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
5 March 2013Application submitted
4 June 2013Planning permission granted
16 November 2015Construction started
11 March 2016Operational

Project details

Technology
solar farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
18 August 2016
Operator or applicant
Lightsource BP
Planning authority
King's Lynn and West Norfolk
Planning application reference
13/00336/FM
Site area
55.2 ha
Address (REPD)
Leicester Square Farm Leicester Road South Creake Norfolk
Council area (by location)
King's Lynn and West Norfolk
Time to decision
13 weeks
REPD reference
1777

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chiplowwind farm8.2operational5.4
Jack's Lane Wind Farmwind farm13.8operational6.1
North Creake Airfieldsolar farm20operational6.3
Jack's Lane Solarsolar farm5permission expired6.5
West Raynhamsolar farm49.9operational8.1
Shereford Road, West Raynham Estatebattery storage50approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8619, 0.7713).