Jack's Lane Solar (5 MW)

Jack's Lane Solar is a 5 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 11 February 2019; the record was last updated on 25 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
25 June 2020record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
22 October 2015Application submitted
11 February 2016Planning permission granted
11 February 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
25 June 2020
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
King's Lynn and West Norfolk
Planning application reference
15/01701/FM
Address (REPD)
land west of the B1454
Council area (by location)
King's Lynn and West Norfolk
Time to decision
16 weeks
REPD reference
5173

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jack's Lane Wind Farmwind farm13.8operational1.5
Chiplowwind farm8.2operational2.0
South Creake Solar Farmsolar farm26operational6.5
Sedgeford Hall Estate Solar Panels & Battery Storagesolar farm21approved, not built8.3
Thornham Solar Farmsolar farm15abandoned9.1
Sedgefordwind farm10.8application withdrawn9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8722, 0.6761).