Thornham Solar Farm (15 MW)

Thornham Solar Farm is a 15 MW solar farm project in King's Lynn and West Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
abandonedstatus in REPD
15 April 2015record last updated
King's Lynn and West Norfolkcouncil area

Planning timeline

DateStage
14 January 2013Application submitted
15 April 2013Planning permission granted
15 April 2014Permission expired

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
abandoned
Record last updated
15 April 2015
Operator or applicant
Lark Energy
Planning authority
King's Lynn and West Norfolk
Planning application reference
13/00049/FM
Address (REPD)
Lyng Farm Burnham Road Thornham Hunstanton
Council area (by location)
King's Lynn and West Norfolk
Time to decision
13 weeks
REPD reference
1870

Earlier applications for this site

ApplicationMWSubmittedOutcome
Thornham Solar Farm 12/01505/FM1517 September 2012refused 10 December 2012

Who decides

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sedgefordwind farm10.8application withdrawn6.2
Sedgeford Hall Estate Solar Panels & Battery Storagesolar farm21approved, not built6.2
Jack's Lane Wind Farmwind farm13.8operational8.7
Jack's Lane Solarsolar farm5permission expired9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9335, 0.586).